NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION
DT 07-011
MASTER LIST OF EXHIBITS
(ALL PARTIES)
|
Date |
EXH NO. |
DESCRIPTION |
|
BayRing 1 |
Prefiled Direct Testimony of Benjamin P. Thayer on Behalf of BayRing (Admitted for Limited Purposes) |
|
CLECs 1 |
Prefiled Direct Testimony of Gary J. Ball on Behalf of BayRing, segTEL and Otel (Admitted for Limited Purposes) |
|
segTEL 1 |
Prefiled Direct Testimony of Jeremy L. Katz on Behalf of segTEL (Admitted for Limited Purposes) |
|
segTEL2 |
Town of Hanover’s Responses to segTEL Data Requests and Accompanying Affidavit |
10/22/07 |
FRP 1 |
Rebuttal Testimony of Brian Lippold |
10/22/07 |
FRP 2 |
Direct Testimony of Michael Haga |
10/22/07 |
FRP 3P |
Public Version of Joint Rebuttal Testimony of Michael Haga and Arthur Kurtz |
|
FRP 3C |
Joint Rebuttal Testimony of Michael Haga and Arthur Kurtz Confidential |
10/25/07 |
FRP 4 |
Rebuttal Testimony of Michael T. Skrivan |
10/29/07 |
FRP 5 |
Rebuttal Testimony of Douglas C. Sicker, Ph.D |
10/29/07 |
FRP 6 |
Direct Testimony of Peter G. Nixon |
10/31/07 |
FRP 6 Errata |
Errata page 9 of Direct Testimony of Peter G. Nixon |
10/29/07 |
FRP 7 |
Rebuttal Testimony of Peter G. Nixon |
10/23/07 |
FRP 8P |
Public Version of Pre-Filed Testimony of Walter E. Leach, Jr. |
|
FRP 8C |
Pre-Filed Testimony of Walter E. Leach, Jr. Confidential |
10/31/07 |
FRP 9P |
Public Version of Rebuttal Testimony of Walter E. Leach, Jr. |
|
FRP 9C |
Rebuttal Testimony of Walter E. Leach, Jr. Confidential |
|
FRP 9HC |
Rebuttal Testimony of Walter E. Leach, Jr. Highly Confidential |
10/24/07 |
FRP 10P |
Public Version of Pre-Filed Rebuttal Testimony of William E. King |
|
FRP 10C |
Pre-Filed Rebuttal Testimony of William E. King Confidential |
|
FRP 10HC |
Pre-Filed Rebuttal Testimony of William E. King Highly Confidential |
10/24/07 |
FRP 11P |
Public Version of Pre-Filed Direct Testimony of Michael J. Balhoff |
|
FRP 11C |
Pre-Filed Direct Testimony of Michael J. Balhoff Confidential |
10/24/07 |
FRP 12P |
Public Version of Rebuttal of Michael J. Balhoff |
|
FRP 12C |
Rebuttal of Michael J. Balhoff Confidential |
10/29/07 |
FRP 13 |
Direct Testimony of Michael J. Harrington |
10/29/07 |
FRP 14P |
Public Version of Joint Rebuttal Testimony of Michael Brown, Michael Harrington and John Smee |
|
FRP 14C |
Joint Rebuttal Testimony of Michael Brown, Michael Harrington and John Smee Confidential |
10/22/07 |
FRP 15 |
Settlement Stipulation Among FairPoint Communications, Inc., Freedom Ring Communications, LLC, d/b/a BayRing Communications, LLC, segTEL, Inc. and Otel Telekom, Inc. |
10/22/07 |
FRP 16 |
Oral Data Request - potential increase in cost of TSA |
10/22/07 |
FRP 17P |
Oral Data Request - Public version - unredacted copies of Work Orders 1 and 2 |
|
FRP 17C |
Oral Data Request - unredacted copies of Work Orders 1 and 2 Confidential |
|
FRP 17HC |
Oral Date Request - unredacted copies of Work Orders 1 and 2 Highly Confidential |
10/22/07 |
FRP 18 |
Oral Data Request - reference in Hawaii Telcom S-4 |
|
FRP 19 |
Testing Strategies Document (on disk) |
|
FRP 20 |
Joint Application for Approval of Transfer |
|
FRP 21 |
Agreement and Plan of Merger dated January 15, 2007 |
|
FRP 22 |
Distribution Agreement |
|
FRP 23 |
Transferor’s Pre-Merger Corporate Structure |
|
FRP 24 |
Description of the Proposed Transaction |
|
FRP 25 |
Transition Services Agreement |
|
FRP 26 |
Randy Barber’s Response to Maine Data Request FP I-4-10 |
|
FRP 27 |
Randy Barber’s Response to Maine Data Request FP I-4-11 |
|
FRP 28 |
Randy Barber’s Response to Maine Data Request FP I-4-12 |
|
FRP 29 |
Randy Barber’s Response to Maine Data Request FP I-4-13 |
|
FRP 30 |
Randy Barber’s Response to Maine Data Request FP I-4-14 |
|
FRP 31 |
Randy Barber’s Response to Maine Data Request FP I-4-20 |
|
FRP 32 |
Randy Barber’s Response to Maine Data Request FP I-4-32 |
|
FRP 33 |
Randy Barber’s Response to NH Data Request FP: Labor-14 |
|
FRP 34 |
Cover Page of Embarq Corp. 10-K and Embarq Corp. Consolidated Balance Sheets |
10/25/07 |
FRP 35 |
Cover Page of Embarq Corp. Information Statement and Risk Factors |
|
FRP 36 |
Cover Page of Alltel/Valor Proxy Statement/Prospectus-Information Statement and Risk Factors |
|
FRP 37 |
Direct Testimony of David Brevitz before PSC of Kentucky – 2005-00534 |
10/22/07 |
FRP 38 |
Verizon New England Earnings Statement – 12/31/06 |
|
FRP 39 |
Link for S-4/A Filing on Edgar |
|
FRP 40 |
Reserved |
|
FRP 41 |
Reserved |
|
FRP 42 |
Reserved |
|
FRP 43 |
Reserved |
10/23/07 |
FRP 44P |
Oral Data Request- Public version - credit rating agencies’ evaluations after merger close |
|
FRP 44C |
Oral Data Request- credit rating agencies’ evaluations after merger close Confidential |
10/23/07 |
FRP 45 |
Oral Data Request - (a) difference between purchase price and net book value and accounting treatment;
(b) how is difference treated in a rate case |
10/23/07 |
FRP 46P |
Oral Data Request - Public version of documentation of figure for cost of good sold for DSL per line, per month |
|
FRP 46HC |
Oral Data Request - version of documentation of figure for cost of good sold for DSL per line, per month Highly confidential |
10/23/07 |
FRP 47 |
Oral Data Request - terms and compensation of SpinCo BOD |
10/23/07 |
FRP 48P |
Oral Data Request - Public version of modeling for declining number of switch access lines over next 5 years |
|
FRP 48HC |
Oral Data Request - version of modeling for declining number of switch access lines over next 5 years Highly Confidential |
|
FRP 49C |
Oral Data Request – Confidential access lines for SpinCo at end of 2009 |
10/25/07 |
FRP 50 |
Oral Data Request - provision of Act which would impose obligations similar to those imposed on BOCS by 272(e) |
10/25/07 |
FRP 51 |
Oral Data Request - person who determined cost per DSL line per month |
10/25/07 |
FRP 52C |
Oral Data Request –ratepayers share of Broadband expansion Confidential |
10/26/07 |
FRP 53 |
Oral Data Request - if there are disagreements under RLEC settlements, are expenses recoverable from ratepayers |
10/26/07 |
FRP 54HC |
Oral Data Request –access rates Highly Confidential |
10/26/07 |
FRP 55 |
Oral Data Request - outside plant reviews |
10/29/07 |
FRP 56 |
Oral Data Request - DSL pricing |
10/29/07 |
FRP 57 |
Oral Data Request - all marketing literature |
10/29/07 |
FRP 58 |
Oral Data Request - preliminary emergency service plan |
10/29/07 |
FRP 59P |
Oral Data Request - Public version of Broadband plan |
|
FRP 59C |
Oral Data Request - Broadband plan Confidential |
|
FRP 59HC |
Oral Data Request - Broadband plan Highly Confidential |
10/29/07 |
FRP 60 |
Oral Data Request - OneComm partial agreement |
10/29/07 |
FRP 61 |
Oral Data Request - number of dedicated personnel |
10/29/07 |
FRP 62 |
Oral Data Request - updated organizational chart |
|
FRP 63 |
Peres Response to FP Labor-29 |
|
FRP 64 |
Peres Response to FP Labor-35 |
|
FRP 65 |
Peres Response to FP Labor-40 |
|
FRP 66 |
CWA January 2007 Paper |
|
FRP 67 |
CWA October 2006 Paper |
|
FRP 68 |
CWA/IBEW Mtg with VT Governor |
|
FRP 69 |
CWA/IBEW Campaign to Block Verizon Sale |
10/30/07 |
FRP 70 |
Exhibit 70 |
|
FRP 70C |
Oral Data Request - What is the total dollar amount that would be transferred to Verizon if the transaction is approved. |
|
FRP 71HC |
Oral Data Request –if transaction rejected what is the cost to FairPoint Highly Confidential |
10/30/07 |
FRP 72 |
Oral Data Request - migration of voice traffic |
10/30/07 |
FRP 73 |
Oral Data Request - copies of press releases related to WiFi in Westfield |
|
FRP 74 |
Updated Business Integration Operations: Design, Build & Launch |
|
FRP 75C |
Settlement Agreement - PAETEC and FairPoint Confidential |
|
FRP 76C |
Settlement Agreement - DSCI and FairPoint Confidential |
|
FRP 77C |
Settlement Agreement - Level 3 and FairPoint Confidential |
02/04/08 |
FRP 78 |
Settlement Agreement – Among the Joint Petitioners and the Staff |
02/04/08 |
FRP 79 |
State of Maine – Amended Stipulation 12/21/2007 |
02/04/08 |
FRP 80 |
Stipulation Among Fairpoint, VZ and the VT DPS Docket 7270 |
02/04/08 |
FRP 81 HC |
FairPoint Project Nor’easter table Highly Confidential |
03/30/08 |
FRP 82 HC |
FairPoint Project Nor’easter table Assumptions Summary Highly Confidential |
03/30/08 |
FRP 83 |
JP Morgan Report |
03/30/08 |
FRP 84 |
Lehman Brothers Report |
03/30/08 |
FRP 85 |
LCD News List e-mail |
03/30/08 |
FRP 86 HC |
Project Nor’easter table Financial Summary Highly Confidential |
|
Labor 1P |
Direct testimony of Kenneth Peres |
|
Labor 2P |
Public direct testimony of Randy Barber |
|
Labor 3C |
Direct testimony of Randy Barber - version (redacts Highly Confidential information) Confidential |
|
Labor 3HC |
Direct testimony of Randy Barber - Highly Confidential |
|
Labor 4C |
FairPoint’s commitment letter for financing, dated January 15, 2007 Confidential |
|
Labor 5P |
FairPoint’s existing senior credit agreement |
|
Labor 6P |
Order of Illinois Commerce Commission, Docket 04-0299, dated May 26, 2004 |
|
Labor 7P |
Affidavit of Walter Leach, Illinois Commerce Commission, Docket 04-0299, dated December 20, 2004 |
|
Labor 8P |
Order of Illinois Commerce Commission, Docket 04-0299, dated January 20, 2005 |
|
Labor 9P |
Order of Illinois Commerce Commission, Docket 07-0191, dated June 27, 2007 |
|
Labor 10P |
Order of New York Public Service Commission, Case 03-C-0972, dated March 16, 2005 |
|
Labor 11HC |
Excerpts from FairPoint’s synergies model Highly Confidential |
|
Labor 12HC |
Excerpts from FairPoint’s financial model Highly Confidential |
|
Labor 13P |
Excerpts from W. King’s work papers |
02/04/08 |
Labor 14P |
Additional Testimony Randy Barber Redacted Version |
02/04/08 |
Labor 14HC |
Additional Testimony Randy Barber Super Confidential Highly Confidential |
02/04/08 |
Labor 15HC |
Labor Exh.A1-HC; Discovery Model Worksheets Highly Confidential |
|
JT Munis 1P |
Pre-filed Testimony of Julia Griffin |
|
JT Munis 2P |
Pre-filed Testimony of Jeffrey Brown |
|
JT Munis 3P |
Pre-filed Testimony of Richard Malasky |
|
JT Munis 4P |
FairPoint Response to Municipal DR 2-5 |
|
JT Munis 5P |
FairPoint Response to Municipal DR 2-6 |
|
JT Munis 6P |
FairPoint Response to Municipal DR 5-3 |
|
JT Munis 7P |
FairPoint Response to Municipal DR 5-4 |
|
JT Munis 8P |
FairPoint Response to Municipal DR 5-5 |
|
JT Munis 9P |
FairPoint Response to Municipal DR 5-6 |
|
JT Munis 10P |
FairPoint Response to Municipal DR 5-8 |
|
NGrid 1P |
Pre-filed Direct Testimony of Cheryl A. Warren |
|
NGrid 2P |
Memorandum of Understanding between National Grid and FairPoint |
10/31/07 |
NECTA/CPNH 1P |
Pre-filed Direct Testimony of Michael D. Pelcovits, Public Version with attachments MDP-1 through MDP-51 |
10/31/07 |
NECTA/CPNH 1C |
Pre-filed Direct Testimony of Michael E. Pelcovits, with attachments MDP-1 through MDP-51 Confidential |
|
NECTA/CPNH 2P |
NECTA-CPNH:FP - 16R |
|
NECTA/CPNH 2C |
NECTA-CPNH:FP - 114R - Confidential |
10/22/07 |
NECTA/CPNH 3C |
FairPoint Cutover Tasks Index - Confidential |
|
NECTA/CPNH 3P |
NECTA-CPNH:FP - 17R |
10/22/07 |
NECTA/CPNH 4C |
Work Order No. 1 To Master Service Agreement - Withdrawn: part of FairPoint’s exhibits - Confidential |
|
NECTA/CPNH 4P |
NECTA-CPNH - 20R |
|
NECTA/CPNH 5P |
NECTA-CPNH - 34R |
|
NECTA/CPNH 5C |
Work Order No. 2 to Master Services Agreement - Withdrawn: part of FairPoint’s exhibits - Confidential |
|
NECTA/CPNH 6C |
FairPoint Combined and Spinco Only Projected Financials - Confidential |
|
NECTA/CPNH 6P |
NECTA-CPNH FP - 42R |
|
NECTA/CPNH 7P |
NECTA-CPNH FP - 44R |
10/22/07 |
NECTA/CPNH 7C |
RDR 86 - Confidential |
10/22/07 |
NECTA/CPNH 8C |
Nor’Easter Program Test Strategy - Confidential |
|
NECTA/CPNH 8P |
NECTA-CPNH FP - 53R |
|
NECTA/CPNH 9P |
NECTA-CPNH FP - 67R |
|
NECTA/CPNH 10P |
NECTA-CPNH FP - 26R |
|
NECTA/CPNH 11P |
NECTA-CPNH FP - 27R |
|
NECTA/CPNH 12P |
NECTA-CPNH FP - 30R |
|
NECTA/CPNH 13P |
NECTA-CPNH FP - 31R |
|
NECTA/CPNH 14P |
NECTA-CPNH FP - 33R |
|
NECTA/CPNH 15P |
NECTA-CPNH FP - 35R |
|
NECTA/CPNH 16P |
NECTA-CPNH FP - 36R |
|
NECTA/CPNH 17P |
NECTA-CPNH FP - 37R |
|
NECTA/CPNH 18P |
NECTA-CPNH FP - 38R |
|
NECTA/CPNH 19P |
NECTA-CPNH FP - 39R |
|
NECTA/CPNH 20P |
NECTA-CPNH FP - 43R |
10/22/07 |
NECTA/CPNH 21P |
NECTA-CPNH FP - 46R |
|
NECTA/CPNH 22P |
NECTA-CPNH FP - 47R |
10/22/07 |
NECTA/CPNH 23P |
NECTA-CPNH FP - 49R |
|
NECTA/CPNH 24P |
NECTA-CPNH FP - 50R |
|
NECTA/CPNH 25P |
CLEC’s FP - R13 |
|
NECTA/CPNH 26P |
CLEC’s FP - R21 |
|
NECTA/CPNH 27P |
CLEC’s FP - R22 |
|
NECTA/CPNH 28P |
NECTA-CPNH FP - 18R |
|
NECTA/CPNH 29P |
NECTA-CPNH FP – 19R |
10/22/07 |
NECTA/CPNH 30P |
CLEC’s FP – R41 |
|
NECTA/CPNH 31P |
CLEC’s FP – R37 |
|
NECTA/CPNH 32P |
CLEC’s FP - R36 |
|
NECTA/CPNH 33P |
NECTA-CPNH FP - 24R |
|
NECTA/CPNH 34P |
NECTA-CPNH FP - 21R |
|
NECTA/CPNH 35P |
CLEC FP III-2-15 |
|
NECTA/CPNH 36P |
CLEC FP III-1-24 |
|
NECTA/CPNH 37P |
CLEC FP III-1-25 |
|
NECTA/CPNH 38P |
CLEC FP III-2-22 |
|
NECTA/CPNH 39P |
CLEC FP III-2-22 (duplicate no. 22) |
|
NECTA/CPNH 40P |
CLEC FP III-2-23 |
|
NECTA/CPNH 41P |
CLEC FP III -3-19 |
|
NECTA/CPNH 42P |
CLEC FP III-3-20 |
|
NECTA/CPNH 43P |
NECTA-CPNH FP - 70R |
10/22/07 |
NECTA/CPNH 44P |
NECTA-CPNH FP - 71R |
10/22/07 |
NECTA/CPNH 45P |
NECTA-CPNH FP - 72R |
10/22/07 |
NECTA/CPNH 46P |
NECTA-CPNH FP - 74R |
|
NECTA/CPNH 47P |
NECTA-CPNH FP - 76R |
|
NECTA/CPNH 48P |
NECTA-CPNH FP - 77R |
|
NECTA/CPNH 49P |
NECTA-CPNH FP - 78R |
10/22/07 |
NECTA/CPNH 50P |
NECTA-CPNH FP - 80R |
|
NECTA/CPNH 51P |
NECTA-CPNH FP - 83R |
|
NECTA/CPNH 52P |
NECTA-CPNH FP - 85R |
|
NECTA/CPNH 53P |
NECTA-CPNH FP - 86R |
|
NECTA/CPNH 54P |
NECTA-CPNH FP - 87R |
|
NECTA/CPNH 55P |
CLEC FP III-1-16 |
|
NECTA/CPNH 56P |
CLEC FP III-1-42 |
|
NECTA/CPNH 57P |
CLEC FP III-1-14 |
|
NECTA/CPNH 58P |
NECTA-CPNH VZ GI-1-1 |
|
NECTA/CPNH 59P |
NECTA-CPNH VZ GI-1-2 |
|
NECTA/CPNH 60P |
NECTA-CPNH VZ GI-1-3 |
|
NECTA/CPNH 61P |
NECTA-CPNH VZ GI-1-9 |
|
NECTA/CPNH 62P |
NECTA-CPNH VZ GI-1-13 |
|
NECTA/CPNH 63P |
NECTA-CPNH VZ GI-1-14 |
|
NECTA/CPNH 64P |
NECTA VZ G5-1-89 |
|
NECTA/CPNH 65P |
NECTA VZ G5-1-91 |
|
NECTA/CPNH 66P |
NECTA-CPNH VZ GI-1-16 |
|
NECTA/CPNH 67P |
NECTA VZ G5-1-101 |
|
NECTA/CPNH 68P |
NECTA VZ G5-1-105 |
|
NECTA/CPNH 69P |
ONE COMM VZ GI-1-20 |
|
NECTA/CPNH 70P |
BAYRING VZ GI-1-11 |
|
NECTA/CPNH 71P |
BAYRING VZ GI-1-12 |
|
NECTA/CPNH 72P |
NECTA-CPNH VZ - R3 |
|
NECTA/CPNH 73P |
NECTA-CPNH VZ - R5 |
|
NECTA/CPNH 74P |
NECTA-CPNH VZ - R6 |
|
NECTA/CPNH 75P |
NECTA-CPNH VZ - R8 |
|
NECTA/CPNH 76P |
NECTA-CPNH VZ - R9 |
|
NECTA/CPNH 77P |
NECTA-CPNH VZ - R10 |
|
NECTA/CPNH 78P |
NECTA-CPNH VZ - R11 |
|
NECTA/CPNH 79P |
NECTA-CPNH VZ - R12 |
|
NECTA/CPNH 80P |
NECTA-CPNH VZ - R14 |
|
NECTA/CPNH 81P |
NECTA-CPNH VZ - R15 |
10/22/07 |
NECTA/CPNH 82P |
Excerpt from FairPoint SEC S-4 filing identifying proposed merger risk factors |
10/22/07 |
NECTA/CPNH 83P |
Excerpt from FairPoint Initial Brief in Vermont Public Service Board Docket No. 7270, cover page and pages 88-101 |
02/04/08 |
NECTA/CPNH 84P |
VZ/ Fairpoint Motion to approve VZ VT transaction DRM 01/08/08 |
02/04/08 |
NECTA/CPNH 85P |
Stipulation among FairPoint VZ and VT DPS DRM 01/08/08 |
02/04/08 |
NECTA/CPNH 86P |
VT PSBd; Hearings Transcripts September 2007 |
02/04/08 |
NECTA/CPNH 87P |
State of Maine, Docket 2005-155 Amended Stipulation |
| |
|
|