| 25,061 |
12/31/09 |
DE 09-180 |
Public Service Company of New Hampshire |
2010 Default Energy Service Rate - Order Approving 2010 Energy Service Rate |
| 25,060 |
12/31/09 |
DE 09-091 |
Public Service Company of New Hampshire |
Reconciliation of Energy Service and Stranded Cost Charges for 2008 - Order Approving Settlement Agreement |
| 25,059 |
12/31/09 |
DE 09-158 |
Public Service of New Hampshire |
Tariff Filing to Modify Demand Response Options - Order Approving Motion for Permission to Withdraw Petition |
| 25,057 |
12/29/09 |
DE 09-234 |
Granite State Electric Company D/B/A National Grid |
Petition for Approval of 2010 Retail Rate Adjustments - Order Approving Rate Adjustments
|
| 25,056 |
12/22/09 |
DE 09-179 |
Public Service Company of New Hampshire |
Petition for 2010 Stranded Cost Recovery Charge - Order Approving Updated Petition
|
| 25,055 |
12/21/09 |
DE 09-010 |
Granite State Electric Company D/B/A National Grid |
Petition for Approval of Proposed Default Service Rates for February 1, 2010 through April 30, 2010 for Large Commercial and Industrial Customers - Order Approving Petition
|
| 25,054 |
12/18/09 |
DE 09-009 |
Unitil Energy Systems, Inc. |
Petition for Approval of Default Service Solicitation And Proposed Default Service Tariffs For Large Commercial and Industrial Customers - Order Approving Petition |
| 25,052 |
12/14/09 |
DE 09-226 |
New Hampshire Electric Cooperative |
Petition for 2010 Stranded Cost Charge - Order Nisi Granting Petition |
| 25,050 |
12/08/09 |
DE 09-033 |
Public Service Company of New Hampshire |
Petition for Issuance of Long-Term Debt, Mortgaging of Property,
Execution of an Interest Rate Transaction and Increase in Short-Term Debt - Order Denying
Motions for Rehearing |
| 25,049 |
12/03/09 |
DE 09-137 |
Unitil Energy Systems, Inc. |
Petition for Approval of Investment in Distributed Energy Resources - Order Further Suspending Tariff |
| 25,048 |
11/30/09 |
DE 09-180 |
Public Service Company of New Hampshire |
Proposed Default Energy Service Rate--2010 - Order on Motions to Compel |
| 25,046 |
11/20/09 |
DE 08-135 |
Public Service Company of New Hampshire |
Tariff Filing Revising Line Extension Policy - Order Approving Settlement Agreement |
| 25,042 |
11/9/09 |
DE 09-155 |
Unitil Energy Systems, Inc. |
Petition Requesting an Accounting Order - Order Approving Petition |
| 25,037 |
10/30/09 |
DE 09-035 |
Public Service Company of New Hampshire |
Petition for Permanent Rate Increase - Order on Motions for Confidential Treatment and Waiver of Filing Requirements |
| 25,027 |
10/22/09 |
DE 08-085 |
Unitil Energy Systems, Inc. |
Petition for Approval of Increase to Short-Term Debt Limit - Order Nisi Approving Settlement Agreement |
| 25,026 |
10/9/09 |
DE 09-186 |
Public Service Company of New Hampshire |
Request for Approval of a Renewable Default Service Rate - Order Suspending Tariff and Scheduling Prehearing Conference |
| 25,023 |
10/7/09 |
DE 09-124 |
Public Service Company of New Hampshire |
Petition for License to Construct and Maintain Electric Lines Over and Across the Public Waters of the Bellamy River in Dover, New Hampshire - Order Nisi Granting License |
| 25,021 |
10/5/09 |
DE 09-033 |
Public Service Company of New Hampshire |
Petition for the Issuance of Long-Term Debt, Mortgaging of Property, Execution of an Interest Rate Transaction and Increase in Short-Term Debt Limit - Order Approving Petition |
| 25,020 |
10/2/09 |
DE 09-054 |
Residential Electric Generation Incentive Program |
Order Approving Application for Prospective Installations |
| 25,015 |
9/22/09 |
DE 09-135 |
State-Wide Low Income Electric Assistance Program |
2009-2010 Program Budgets - Order Nisi Approving 2009-2010 Program Budgets |
| 25,013 |
9/21/09 |
DE 09-010 |
Granite State Electric Company D/B/A National Grid |
Petition for Approval of Proposed Default Service Rates for the Large and Small Customer Groups for the Period beginning November 1, 2009 - Order Approving Petition |
| 25,011 |
9/4/09 |
DE 09-009 |
Unitil Energy Systems, Inc. |
Petition for Approval of Default Service Solicitation and Proposed Default Service Tariffs - Order Approving Petition |
| 25,010 |
9/4/09 |
DE 09-137 |
Unitil Energy Systems, Inc. |
Petition for Approval of Investment in and Rate Recovery for Distributed Energy Resources - Order Suspending Tariff and Scheduling a Prehearing Conference |
| 25,008 |
9/1/09 |
DE 08-145 |
Freedom Logistics, LLC and Halifax-American Energy Company |
Petition for Investigation into Modifications at Merrimack Station - Order Denying Petition |
| 25,001 |
8/6/09 |
DE 09-033 |
Public Service Company of New Hampshire |
Petition for Increase to Short Term Debt Limit and to Issue Long Term Debt - Order Denying Motion to Compel |
| 24,998 |
7/31/09 |
DE 09-094 |
Granite State Electric Company d/b/a National Grid |
2009 Annual Reliability Enhancement and Vegetation Management Program Results and Reconciliation. It is an Order Approving Petition. |
| 24,997 |
7/31/09 |
DE 09-035 |
Public Service Company of New Hampshire |
Petition for Permanent Rate Increase. It is an Order Approving Temporary Rates |
| 24,994 |
7/31/09 |
DE 09-035 |
Public Service Company of New Hampshire |
Petition for Permanent Rate Increase. It is an Order Suspending Tariffs and scheduling Prehearing Conference, |
| 24,993 |
7/24/09 |
DE 09-115 |
Unitil Energy Systems, Inc. |
Annual Stranded Cost Recovery and External Delivery Charge Reconciliation and Rate Filing - Order Following Hearing
|
| 24,992 |
7/24/09 |
DE 09-114 |
Public Service Company of New Hampshire |
Petition for Revised Transmission Cost Adjustment Mechanism Rate - Order Approving Revised Rate
|
| 24,991 |
7/24/09 |
DE 08-113 |
Public Service Company of New Hampshire |
Proposed Mid-Term Adjustment to 2009 Energy Service Rate - Order Approving Petition
|
| 24,990 |
7/24/09 |
DE 06-061 |
Investigation Into Energy Policy Act Of 2005 |
Request for Suspension of Tariffs - Order Suspending Tariffs
|
| 24,987 |
7/23/09 |
DE 08-114 |
Public Service Company of New Hampshire |
Petition for Interim Change to Stranded Cost Recovery Charge - Order Approving Petition |
| 24,985 |
7/14/09 |
DE 09-054 |
Residential Renewable Energy Generation |
Incentive Program - Order Approving Application for Installed Facilities |
| 24,982 |
6/25/09 |
DE 08-077 |
Public Service Company of New Hampshire |
Petition for Approval of Power Purchase and REC Option Agreements between Public Service Company
of New Hampshire and Lempster Wind, LLC - Order Denying Motion for Rehearing |
| 24,981 |
6/19/09 |
DE 09-010 |
Granite State Electric Company D/B/A National Grid |
Petition for Approval of Proposed Default Service Rates for August 1, 2009 through October 31, 2009 for Large Commercial and Industrial Customers - Order Approving Petition |
| 24,980 |
6/19/09 |
DE 09-009 |
Unitil Energy Systems, Inc. |
Petition for Approval of Default Service Solicitation And Proposed Default Service Tariffs For Large Commercial and Industrial Customers - Order Approving Petition |
| 24,979 |
6/19/09 |
DE 09-033 |
Public Service Company of New Hampshire |
Petition for Increase to Short Term Debt Limit and to Issue Long Term Debt - Order Defining Scope of Proceeding |
| 24,974 |
6/4/09 |
DE 08-120 |
2009 Core Energy Efficiency Programs |
Proposed Fuel Blind Home Energy Solutions Pilot Program - Order Nisi Approving Modified Fuel Blind Program
|
| 24,973 |
6/1/09 |
DE 09-075 |
Public Service Company of New Hampshire |
Petition for License to Construct and Maintain Electric Lines Over and Across the Public Waters of the Nubanusit Brook in the Town of Peterborough, New Hampshire - Order Nisi Granting License
|
| 24,966 |
5/1/09 |
DE 07-108 |
Public Service Company of New Hampshire |
2007 Least Cost Integrated Resource Plan - Order Denying Motions for Rehearing |
| 24,965 |
5/1/09 |
DE 08-077 |
Public Service Company Of New Hampshire |
Petition for Approval of a Power Purchase Agreement and a Renewable Energy Certificate Option Agreement with Lempster Wind, LLC - Order Granting Petition |
| 24,960 |
4/22/09 |
DE 07-045 |
Briar Hydro Associates |
Petition for Declaratory Ruling - Order Denying Motion for Rehearing
|
| 24,956 |
4/8/09 |
DE 08-003 |
New England Power Company d/b/a National Grid |
Petition for License to Construct and Maintain Electric Lines Over and Across Public Waters in the Towns of Walpole and Surrey, NH - Order Nisi Granting License
|
| 24,953 |
3/23/09 |
DE 09-010 |
Granite State Electric Company D/B/A National Grid |
Petition for Approval of Proposed Default Service Rates for the Large and Small Customer Groups for the Period beginning May 1, 2009 - Order Approving Petition
|
| 24,952 |
3/23/09 |
DE 08-053
DE 08-123
and
DE 08-124 |
Public Service Company of New Hampshire
FPL Energy Maine Hydro, LLC |
Class IV Renewable Energy Certificate Eligibility Application for Certain Existing Small Hydroelectric Facilities - Order Denying Motion for Rehearing
|
| 24,951 |
3/23/09 |
DE 07-064 |
Electric Utilities |
Energy Efficiency Rate Mechanisms - Order Denying Motion for Rehearing
|
| 24,949 |
3/20/09 |
DE 09-009 |
Unitil Energy Systems, Inc. |
Petition for Approval of Default Service Solicitation And Proposed Default Service Tariffs - Order Approving Petition
|
| 24,945 |
2/27/09 |
DE 07-108 |
Public Service Company of New Hampshire |
2007 Least Cost Integrated Resource Plan, Order Accepting Integrated Resource Plan
|
| 24,940 |
2/6/09 |
DE 08-053 |
Public Service Company of New Hampshire |
DE 08-123 and DE 08-124 FPL Energy Maine Hydro, LLC
Class IV Renewable Energy Certificate Eligibility Application for Certain Existing Small Hydroelectric Facilities - Order Consolidating Dockets and Annulling Class IV Source Certification for Certain Hydroelectric Facilities
|
| 24,936 |
2/2/09 |
DE 06-061 |
Investigation Into Standards Of Energy Policy Act 2005 |
Interconnection Tariffs for Inverter Connections - Order Suspending Tariffs
|
| 24,935 |
1/30/09 |
DE 08-164 |
Florida Power & Light Company |
Petition for Approval of Financing for Seabrook Transmission Substation Upgrade, Order Nisi Approving Petition |
| 24,934 |
1/16/09 |
DE 07-064 |
Electric Utilities |
Energy Efficiency Rate Mechanisms - Order Resolving Investigation
|
| 24,933 |
1/16/09 |
DE 08-139 |
Public Service Company of New Hampshire |
Petition for Authority to Serve a Single Customer in Lempster - Order Nisi Approving Petition
|
| 24,931 |
1/16/09 |
DE 08-066 |
Public Service Company of New Hampshire |
Reconciliation of 2007 Stranded Cost and Energy Service Charge - Order Approving Settlement Agreement
|
| 24,930 |
1/5/09 |
DE 08-120 |
2009 Core Energy Efficiency Programs |
Core Energy Efficiency Programs - Order Approving Settlement Agreement
|