DE 11-182

FIRST WIND ENERGY, LLC

Application for Certification as a REC Eligible Facility Stetson Wind II, LLC-Stetson II

TAB

DATE

DESCRIPTION

FILED BY

1

09/02/11

Statement of Intent to File Motion for Confidential Treatment

Elizabeth Weir

2

09/12/11

Application for Certification as a REC Eligible Facility Stetson Wind II, LLC-Stetson II
Confidential Material in Commission File

  • Cover Letter
  • Motion for Confidential Treatment
  • Application
  • Elizabeth Weir

    3

    08/18/11

    Sec ltr Acknowledgement

    Debra A. Howland

    4

    09/12/11

    SW II-Stetson II Request that submitted material dated 08-17-11 be removed from docket and destroyed

    Elizabeth Weir

    5

    09/28/11

    Staff Ltr Request for Additional Information

    Staff

    6

    10/26/11

    SW II-Stetson II Response to Staff Request for Additional Information

  • Cover Letter
  • Response
  • Elizabeth Weir

    7

    11/08/11

    Staff Ltr Request for Additional Information

    Staff

    8

    11/14/11

    SW II-Stetson II Ltr Response to Staff Request for Additional Information

    Elizabeth Weir

    9

    11/22/11

    Staff memo recommendation

    Staff

    10

    11/28/11

    SW II-Stetson II Additional Information

    Elizabeth Weir

    11

    12/05/11

    Sec Ltr Granting Certification

    Case Closed

    Debra A. Howland

    12

    12/07/12

    Staff Memo Recommendation

    Staff

    13

    12/10/12

    Sec Ltr accepting Q1 RECs subject to conditions

    Case Closed

    Debra A. Howland

    14

    11/04/13

    First Wind Ltr updated contact information

    Hallie Flint Gilman

     

     