Home > Regulatory

DE 11-221

GRANITE STATE ELECTRIC COMPANY D/B/A NATIONAL GRID

Storm Recovery Adjustment Factor

TAB

DATE

DESCRIPTION

FILED BY

1

09/30/11

Storm Recovery Adjustment Factor

Cover Letter
Direct Testimony of T. Burns
TOC Schedules of T. Burns
Direct Testimony of K Demmer
TOC Schedules of Demmer
Direct Testimony of J Oliveira
TOC Schedules of J Oliveira

Steven V. Camerino

2

10/03/11

Sec Ltr Acknowledgement

Debra A. Howland

3

10/07/11

Order No. 25,276 suspending tariff and scheduling PHC

NHPUC

4

10/24/11

GSEC Affidavits of Publications-published in the Union Leader and Valley Sun and Eagle Tribune

Donna Schesser

5

10/24/11

Clerk's Report

Staff

6

10/27/11

Staff Ltr Report of Technical Session

Staff

7

11/03/11

Sec Ltr Approving Procedural Schedule

Debra A. Howland

8

11/09/11

Transcript of hearing held on October 24, 2011

Steven E. Patnaude

9

11/10/11

Staff Memo recommendation

Staff

10

11/10/11

Staff ltr requesting cancelling Technical Session

Staff

11

12/06/11

Clerk's Report
Exhibits

Staff

12

12/19/11

Transcript of hearing held on December 6, 2011

Steven E. Patnaude

13

12/28/11

Order No. 25, 307 Allowing Increase to Storm Recovery Adjustment Factor

Case Closed

NHPUC

14

12/30/11

Sec ltr revised page 1 to Order No. 25,307

Debra A. Howland

15

01/04/12

GSEC Tariff 1st revised pg 114

Cover Letter
Tariff page

Steven V. Camerino

16

02/08/12

Staff Ltr Confirms Compliance

1st revised Page 114

Staff

 

 

An Official Web Site for New Hampshire Government