1

01/08/10

Order of Notice

NHPUC

2

01/25/10

GSEC d/b/a National Grid's Petition to Intervene

Cover Letter
Petition

Sarah B. Knowlton

3

01/26/10

OCA ltr of participation

Meredith A. Hatfield

4

01/2710

Affidavit of Publication

Gary Epler

5

01/29/10

Testimony of T. Meissner, R. Letourneau and R. Francazio

Cover Letter
Testimony

Gary Epler

6

02/09/10

Unitil letter of Appearance

Cover Letter
Appearance

Susan S. Geiger

7

02/11/10

Clerk's Report

Staff

8

02/12/10

Proposed procedural schedule

Staff

9

02/23/10

Sec Ltr Procedural Schedule

Debra A. Howland

10

02/25/10

Transcript of hearing held on February 11, 2010

LCR

11

04/15/10

Request for procedural schedule suspension

Staff

12

04/22/10

UES Feb 25 2010 Wind Event Response Review

Gary Epler

13

05/13/10

Sec Ltr rescheduling of hearing

Debra A. Howland

14

07/01/10

Staff request for schedule change

Staff

15

07/06/10

Sec ltr rescheduling of Hearing

Debra A. Howland

16

07/30/10

Staff Report and Recommendation

Cover Letter
Report

Staff

17

08/04/10

Clerk's Report
Exhibit List

Staff

18

08/20/10

Transcript of hearing held on August 4, 2010

Condensed version in commission file

Steven E. Patnaude

19

09/24/10

Order No. 25,148 Approving Staff Report and Recommendations

Case Closed

NHPUC

20

10/22/10

UES Compliance filing and Emergency Response Plan

Cover Letter
Compliance
Emergency Report Plan

Gary Epler

 

 