DR 97-014 Public Service Company of New Hampshire Fuel and Purchased Power Adjustment Clause Order Addressing Disputed Issues O R D E R N O. 22,847 February 10, 1998 APPEARANCES: Gerald M. Eaton, Esq. for Public Service Company of New Hampshire; Dean, Rice and Howard by Anne Davidson, Esq. for the New Hampshire Electric Cooperative, Inc.; James T. Rodier, Esq. for Freedom Energy Company, LLC; Campaign for Ratepayers Rights by Representative Robert Cushing; the New Hampshire Department of Justice by Wynn E. Arnold, Esq. and Martin P. Honigberg, Esq. for Governor Jeanne Shaheen; Office of Consumer Advocate by Michael W. Holmes, Esq. for residential ratepayers; and Eugene F. Sullivan III, Esq. for the Staff of the New Hampshire Public Utilities Commission. I. PROCEDURAL HISTORY Following a March 5, 1997 prehearing conference, Public Service Company of New Hampshire (PSNH), on March 14, 1997, filed with the New Hampshire Public Utilities Commission (Commission) a petition for an adjustment of rates pursuant to the Fuel and Purchased Power Adjustment Clause (FPPAC) for the period from June 1, 1997 through November 30, 1997. PSNH filed testimony and exhibits in support of its request to change the FPPAC rate from a credit of $0.00848 (8.48 mils) per kWh to a charge of $0.00118 (1.18 mils) per kWh, which constitutes an increase of $0.00966 (9.66 mils) per kWh or approximately an 8% increase in rates. On March 24, 1997, the Commission issued Order No. 22,529 which, among other things, set a procedural schedule to govern the Commission's investigation into the proposed FPPAC rate, granted the New Hampshire Electric Cooperative, Inc.'s (NHEC) Motion to Intervene, and granted a motion by PSNH to defer consideration of the prudence of certain nuclear outages and the recovery of the corresponding replacement power costs incurred as a result of those outages. On April 7, 1997, the Commission granted the late filed Motion to Intervene of Freedom Energy Company, LLC (Freedom). On September 5, 1997 the Campaign for Ratepayers Rights (CRR) filed a Motion to Intervene that was granted by secretarial letter on October 2, 1997. The Office of Consumer Advocate (OCA) is a statutorily authorized intervenor. On May 2, 1997, the OCA filed the testimony of Kenneth E. Traum and Commission Staff (Staff) filed the joint testimony of Chester A. Kokoszka, James R. Thyng and Scott J. Joyce. On May 7, 1997 Staff filed the testimony of Michael D. Cannata, Jr. and Eugene F. Sullivan, Jr. On May 9, 1997, four days prior to the scheduled hearings on the merits in this proceeding, PSNH filed a Motion to Suspend the FPPAC proceeding. PSNH asserted the suspension was necessary because it had to dedicate the resources normally expended on FPPAC to attempt to mediate a resolution to its federal court lawsuit filed against the Commissioners as a result of the plan issued in the electric restructuring docket. PSNH also requested that the FPPAC credit of 8.48 mils be reduced to 4.81 mils because the revenues required to be deferred under Paragraph B.(K) of the FPPAC formula had been returned to ratepayers. See, Order No. 22,234 (July 10, 1996). By Order No. 22,604, the Commission granted PSNH's request to suspend the proceeding until July 2, 1997, and to increase the FPPAC rate by reducing the 8.48 mil credit to a 4.81 mil credit. On July 2, 1997, PSNH, with the support of a majority of the parties to the aforementioned mediation process, again requested that the Commission continue to stay the proceeding and maintain the FPPAC credit placed in effect by Order No. 22,604 until August 5, 1997. Because of the support for the continued stay expressed by a majority of the parties, and because there was no immediate need to move forward with the process given that the FPPAC rate is subject to reconciliation, the Commission granted the requested relief. The Commission scheduled a hearing for August 4, 1997, to consider what future actions should be taken after August 5, 1997. Order No. 22,665 (July 21, 1997). On August 1, 1997, PSNH filed another motion to continue the suspension of the docket beyond August 5, 1997. On August 4, 1997, the Commission heard from the parties to the mediation regarding the status of the mediation and granted a further suspension until September 2, 1997. The Commission also scheduled a prehearing conference for September 11, 1997 to develop a new procedural schedule, as the mediation process was expected to be concluded by that point. On September 10, 1997, PSNH filed a request to increase the FPPAC rate, effective October 1, 1997, pursuant to the "trigger mechanism" established by the Commission in Order No. 20,794 (March 23, 1993). Re Public Service Company of New Hampshire, 78 NH PUC 149 (1993). PSNH stated it anticipated an under-recovery of approximately $15 million as of December 1, 1997, and that increasing the FPPAC rate from a credit of $0.00481 per kWh to a charge of $0.0 would reduce the under-recovery to $10 million by December 1, 1997. A number of parties and Staff opposed the request for a separate rate adjustment under the trigger mechanism given that the full FPPAC rate was scheduled to be investigated, reviewed and set on December 1, 1997. The Commission denied PSNH's request to increase the FPPAC rate under the trigger mechanism, stating its preference to entertain potential changes to the FPPAC rate in one proceeding. Order No. 22,769 (October 27, 1997). Thus, this proceeding addresses issues that were to be heard in May of 1997 and issues that have arisen since that time. On November 12, 1997, PSNH filed an Objection and Motion to Strike Portions of the Pre-filed Testimony of the Campaign for Ratepayer Rights relating to Pollution Control Revenue Bonds (PCRBs), an Objection and Motion to Strike Portions of Pre-filed Testimony of Kenneth E. Traum as it related to the sale of Seabrook Unit II parts, and an Objection and Motion to Strike the Pre-filed Testimony of George McCluskey Related to the Topic of Light Loading and the Pre-filed Testimony of Michael D. Cannata, Jr. Related to the Topic of Light Loading, Pollution Control Revenue Bonds and Best Efforts. On November 13, 1997, the Office of the Governor filed an Objection to PSNH's Motion to Strike Testimony of George McCluskey. On November 17, 1997, Granite State Hydropower Assoc., Inc. also entered an Objection to the Acceptance by the Commission of Testimony submitted by George McCluskey and Michael D. Cannata, Jr. on the issue of Light Loading. After hearing oral arguments, the Commission denied the motions to strike. Hearings were held November 14, 17, 19, and 22, 1997; post-hearing briefs were filed on November 25, 1997, by PSNH, the Office of the Governor, CRR, OCA, and Staff. The Commission orally deliberated the issues in dispute on December 1, 1997 and issued Order No. 22,797 (December 3, 1997) implementing an FPPAC rate of 2.66 mils which reflected the December 1, 1997 deliberations. II. POSITIONS OF THE PARTIES AND STAFF 1. (a) Capacity Transfer Agreement A. Public Service Company of New Hampshire PSNH maintained that the $27.4 million it received from Connecticut Light and Power (CL&P) for the transfer of capacity from PSNH to CL&P under the Capacity Transfer Agreement was not an FPPAC issue, but was rather a base rate issue that should be addressed in its base rate filing. Apparently, PSNH took this position because the majority of the costs of the fossil fuel capacity transferred to CL&P are recovered through base rates. Notwithstanding this position, PSNH argued that the FPPAC rate must include the carrying costs and the operation and maintenance expenses of the share of Seabrook capacity transferred to CL&P, and "EA" amortization and operation and maintenance expenses and the fuel costs associated with the share of the fossil fired capacity transferred to CL&P under the Capacity Transfer Agreement. PSNH also maintained that PSNH ratepayers must bear the $10 million in increased power production costs, commonly referred to as a production penalty cost, resulting from this transfer of capacity through the FPPAC rate. PSNH contended that Paragraph 4 of the Joint Recommendations of the State and Northeast Utilities (NU) in DR 89-244, which was entered into to address concerns raised by Staff relative to capacity sales and production penalty costs, was inapplicable to this capacity transfer. PSNH argued that because the Capacity Transfer Agreement was executed by PSNH and CL&P on May 14, 1991 and Paragraph 4 states that the FPPAC rate would not include production penalty costs incurred for contracts entered into after the First Effective Date, May 16, 1991, the Joint Recommendation was inapplicable to this capacity sale. B. Office of the Governor The Office of the Governor generally stated its support for the positions of the Staff and the OCA on this issue. C. Office of the Consumer Advocate The OCA concurred with the position taken by Staff that the revenues from the capacity transfer should flow through FPPAC to ratepayers. The OCA argued that because ratepayers are bearing all of the costs of generation of the transferred capacity, ratepayers were entitled to all of the benefits of the transfer. Because the company proposed no change in base rates, the OCA argued that FPPAC was the only mechanism available to protect ratepayers. D. Freedom Energy Company Based on his role as a Staff Utility Analyst in the review of the Rate Agreement in DR 89-244, Mr. Rodier testified that PSNH's request to recover the production penalty costs resulting from the sale of capacity to CL&P from ratepayers was entirely contrary to the "purpose, intent and understanding of the change effectuated to the Rate Agreement" by the Joint Recommendations. E. Staff Staff argued that the revenues from the capacity transfer should flow through FPPAC because the production penalty costs, all of the costs of the Seabrook Power Contract, and the fuel and Clean Air Act Amendments of 1990 (CAAA) costs of fossil generation were being passed on to ratepayers through FPPAC. Staff argued that the FPPAC formula could be construed in a manner that would provide a mechanism to compensate ratepayers. Staff also noted that the Commission had plenary ratemaking authority under RSA 378:7 to equitably compensate ratepayers for this capacity transfer. 1. (b) Rate Agreement Breach A. Public Service Company of New Hampshire PSNH argued that it had not breached the Rate Agreement as alleged by Staff. With regard to NU's filing of a network transmission tariff at the Federal Energy Regulatory Commission (FERC) which resulted in PSNH's loss of millions of dollars in transmission revenues from the Initial System, PSNH maintained that FERC Orders 888 and 888-A required the filings. PSNH further maintained that Section 11 of the Capacity Transfer Agreement requires that the Agreement be in accordance with the orders of the FERC and, therefore, there was no breach. With regard to Staff's contention that NU had not maintained its pledged units in accordance with good electric utility practices as required under the Capacity Transfer Agreement, PSNH responded that the loss of Millstone III was the only relevant unit affecting the Capacity Transfer Agreement, and that the loss of this capacity to PSNH had been addressed as per the terms of the Capacity Transfer Agreement. PSNH did not address Staff's allegation with regard to the proposed modifications to the New England Power Pool (NEPOOL) agreement filed with the FERC and the consequent ramifications to the Rate Agreement. B. Office of the Governor The Office of the Governor generally stated its support for the positions of the Staff and the OCA on this issue. C. Office of the Consumer Advocate The OCA supported the position taken by Staff that NU had breached the Sharing Agreement and, therefore, the Rate Agreement. D. Staff Staff argued that NU had engaged in a course of conduct effectively resulting in a breach of the Rate Agreement. Staff's argument centered on Section 3 of the Rate Agreement and Section 4 of the Rate Agreement and the Sharing Agreement, and the Capacity Transfer Agreements appended thereto, which it maintained were fundamental bases underlying the Rate Agreement. Staff raised three areas which it alleged constituted a course of conduct by NU amounting to a breach of the Rate Agreement. First, Staff alleged that NU committed in Section 3 of the Rate Agreement to maintain sufficient capacity to assure New Hampshire ratepayers an adequate supply of power. To accomplish this end, NU agreed to maintain certain pledged generating units in accordance with good utility practice. Three of the pledged units are Millstone Point Units I, II and III which comprise approximately 40% of the pledged capacity. Given that both internal and external investigations of the Millstone outages concluded the outages were the result of negligent management of the Units, Staff concluded that NU had failed to meet this obligation. Staff also argued that the loss of Millstone III may also have affected revenues to be paid to PSNH under the current capacity transfer, and may also have affected the production penalty cost resulting from that capacity transfer. Second, NU unilaterally filed a network transmission tariff with the FERC resulting in the loss of millions of dollars to PSNH ratepayers in transmission fees from the NU Initial System while maintaining that PSNH must continue to pay millions of dollars in transmission fees to the Initial System regardless of the new network transmission tariff. Third, NU, as a member of NEPOOL, with the ability to exercise substantial control over that entity, supported a filing with the FERC by NEPOOL that would effectively void the Sharing Agreement and its Capacity Transfer Agreements. With regard to the second and third items, Staff argued that NU had a contractual obligation to meet with the State to attempt to negotiate new arrangements that would provide both the State and NU with the benefit of their initial bargains, which NU failed to do. Staff concluded that these actions, when viewed in their entirety, or as a course of conduct, amounted to bad faith on NU's part and a breach of the Rate Agreement. 2. Treatment of "EA" Costs Following the Fixed Rate Period PSNH and Staff concurred that certain costs currently being recovered through "EA" of FPPAC could be recovered through either FPPAC or base rates. Alternatively, PSNH argued that should the Commission determine that such costs are more appropriately collected through base rates, it should be allowed to recover the incremental costs of the CAAA through FPPAC. 3. Best Efforts A. Public Service Company of New Hampshire PSNH asserted that the State had conceded PSNH exercised its "best efforts" to renegotiate certain Small Power Producer (SPP) agreements under Section 12 of the Rate Agreement, and, therefore, there was no need to defer recovery of portions of current and deferred SPP costs as there was no longer any contractual obligation to fulfill. Assuming, for the sake of argument, there was the possibility of a best efforts breach, PSNH argued that the deferrals that occurred during the Fixed Rate Period constituted sufficient security to ratepayers should the Commission determine PSNH had not exercised its best efforts under the Rate Agreement. B. Office of the Governor The Office of the Governor took no position on this issue at this time. It did, however, take issue with PSNH's characterization of any best efforts concessions by the State. C. Office of the Consumer Advocate The OCA argued that the Commission should not allow PSNH to recover a portion of current SPP costs and a portion of deferred SPP costs because it is apparent PSNH did not exercise best efforts with regard to these costs. Thus, the OCA concluded the Commission should defer recovery of some of these costs until final resolution of the issues in DR 96-148. D. Staff Staff took the position that PSNH had not satisfied its best efforts obligations. Staff specifically noted that PSNH could have easily financed the renegotiated agreement with Bio-Energy Corp. with retained earnings rather than paying an $85 million dividend to its Connecticut parent and, notwithstanding the dividend, still had sufficient cash to consummate the renegotiated agreement. Staff also noted that the Commission had considered the State's concessions with regard to best efforts and found that those concessions were merely evidence of compliance with the best efforts obligation that the Commission would consider in rendering its ultimate decision on this issue. Given the level of SPP deferrals at this time, however, Staff did not see the need to defer recovery of any additional SPP costs for purposes of dealing with best efforts. 4. Light Loading A. Public Service Company of New Hampshire PSNH objected to the testimony of Messrs. McCluskey and Cannata recommending, respectively, that the Commission defer recovery of between $20 million to $50 million to be paid to SPPs, or Qualifying Facilities (QF), on a prospective basis over the next year. PSNH argued that Messrs. McCluskey and Cannata had misinterpreted a response to a data request in DR 94-080 that indicated PSNH was annually paying $20 million to the State's SPPs for power provided to PSNH during periods of light loading. Specifically, PSNH argued that "negative avoided costs" had been included in its calculation of the stream of payments to SPPs under the long term rate orders. PSNH also argued that Messrs. McCluskey and Cannata had misinterpreted the term "operational circumstances" under FERC rules that would justify suspension or curtailment of purchases during periods of minimal load conditions, also known as light loading periods. B. Office of the Governor As alluded to above, Mr. McCluskey testified that the Commission should defer PSNH's recovery through FPPAC of $20 million paid to QFs because payments in that amount may not have been required under 18 C.F.R. 292.304(f). Mr. McCluskey testified that 292.304(f) provides that utilities are allowed to curtail deliveries of power by QFs during periods of "light (i.e., low) loads" because purchases during these periods would result in negative avoided costs, that is, during periods where the QFs would be required to pay utilities for the power delivered. To avoid this anomalous result, Mr. McCluskey testified the FERC adopted 292.304(f) which provides that utilities should cease purchases from QFs during these periods. Relying on a data response from PSNH in DR 94-080 that quantified the amount of money expended annually by PSNH in payments to QFs during light load periods, Mr. McCluskey recommended the Commission defer recovery of $20 million. Mr. McCluskey further testified that the inclusion, or lack thereof, of negative avoided costs in the calculation of long term rates granted QFs had no effect on his analysis or his conclusions with regard to the ramifications of 292.304(f). C. Staff Mr. Cannata concurred with Mr. McCluskey that, pursuant to 292.304(f), a prudent utility should be and should have been curtailing delivery of power from QFs during periods of light load. Staff concluded that the annual figure of $20 million arrived at by PSNH in DR 94-080, however, was in reality closer to $30 million if the effects of lost joint dispatch savings were included in the calculation of the revenue impact of QF purchases during light load periods. Staff further testified that PSNH miscalculated the revenue impact of QF purchases by PSNH during light load periods, thereby understating the cost to ratepayers, because PSNH did not include all of its base load plants in arriving at the $20 million figure. Mr. Cannata testified that the inclusion of all base load plants would increase the $30 million figure to approximately $50 million. Mr. Cannata based his conclusion that PSNH should have been curtailing purchases from QFs during light load periods on PSNH's inability to establish that negative avoided costs were included in the long term avoided cost calculations used to derive the rates paid QFs in New Hampshire. Mr. Cannata testified that he had requested information from PSNH that would have resolved this issue, but PSNH had responded that it could not find, or it had destroyed, the requested information. Mr. Cannata indicated that Mr. McCluskey's testimony raised some interesting points he had not considered relative to "operational circumstances" and "light loading" when negative avoided costs are included in the development of long term avoided cost rates. Given the limited time frame for consideration of this position, however, he testified he did not feel comfortable taking any position regarding that testimony. 5. Unit II Parts A. Public Service Company of New Hampshire PSNH objected to the fact that the OCA had, once again, raised the issue of the appropriate treatment of revenues from the sale of Seabrook Unit II parts such as the Unit II steam generators. PSNH argued that the Commission had conclusively determined in dockets DR 97-042 and DR 96-285 that Seabrook Unit II parts were the property of shareholders, and that any profits realized from the sale of these parts belong exclusively to shareholders. Re Public Service Company of New Hampshire, 80 NH PUC 586 (1995); Re Public Service Company of New Hampshire, 81 NH PUC 1034 (1996). Assuming, arguendo, that the issue was appropriately before the Commission, PSNH reiterated the positions it took in those earlier dockets. PSNH argued that pursuant to the Rate Agreement, the entire value of "old PSNH's" ownership share of Seabrook Unit I and abandoned Unit II, $700 million, had been allocated to Unit I, and, therefore, Unit II was the unregulated property of the shareholders of North Atlantic Energy Company (NAECo), a wholly owned subsidiary of NU. NAECo owns all of PSNH's former share of Seabrook. In support of its position PSNH noted that it had not collected any of North Atlantic Energy Service Company's (NAESCo) share of the protect and preserve costs of Unit II parts through the Seabrook Power Contract. PSNH also argued that the Seabrook Power Contract contains no provision for the recovery of these expenses from PSNH and its ratepayers and, therefore, the parts are logically the sole property of shareholders under the Rate Agreement. B. Office of the Consumer Advocate The OCA argued that ratepayers are currently paying for Unit II parts because $700 million was the value assigned to Seabrook Station, Units I and II under the Rate Agreement. The OCA contended that the $700 million was not allocated to Unit I for the purposes of the Seabrook Power Contract, but rather that the Contract included both Units I and II. Thus, the OCA concluded that the revenue from the sale of Unit II parts, such as the steam generators, should be returned to ratepayers. C. Office of the Governor The Office of the Governor concurred with the position taken by the OCA and expressed concerns raised relative to the tax consequences of Unit II part sales to PSNH. D. Staff Staff indicated that the majority of Staff supported the position of the OCA and requested that the Commission take administrative notice of the testimonies and positions of the Finance Director, Eugene F. Sullivan, Jr, and the Chief Engineer, Michael D. Cannata, Jr., in DR 94-172. Administrative notice was taken without objection. In DR 94-172 the Commission's Engineering Staff and Finance Staff took divergent positions on this issue. Mr. Cannata recommended that the Commission establish an "imprudence mitigation fund" to recognize the extraordinary performance of NAESCo, a wholly owned subsidiary of NU that operates Seabrook Station, in operating Seabrook Unit I. Mr. Cannata argued that an essential element of this extraordinary performance was NAESCo's preservation and maintenance of NAECo's abandoned Unit II parts without compensation. Mr. Cannata represented that the maintenance and preservation of these parts had resulted in unrecognized value to PSNH ratepayers by reducing the amount of time Seabrook would be down because of the availability of these parts. Mr. Cannata proposed that the imprudence mitigation fund be financed from the savings accruing to PSNH ratepayers because of the availability and use of Unit II parts in Unit I. Thus, Mr. Cannata concluded that the parts were not part of the $700 million allocated to Seabrook Station under the Seabrook Power Contract. Mr. Sullivan recommended that the Commission recognize the value of Unit II parts by a pass through of NAECo's share of the revenues from the sale of Unit II parts to PSNH ratepayers through the Seabrook Power Contract. Mr. Sullivan also recommended that it was inappropriate to capitalize Unit II parts as they were placed in service in Unit I. Mr. Sullivan based these recommendations on the language in the Rate Agreement that assigned a $700 million value to "all" of the assets at Seabrook Station, which included Unit II and its parts, and because the entire $700 million, paid for both Units, had been allocated to Unit I for the purposes of the Seabrook Power Contract. 6. Pollution Control Revenue Bonds A. Public Service Company of New Hampshire In response to CRR's contention that the lower cost of debt on certain tax exempt Pollution Control Revenue Bonds (PCRBs) comprising a part of PSNH's capital structure should be imputed to NAECo's capital structure for the purposes of the Seabrook Power Contract during the Fixed Rate Period, PSNH raised a number of arguments in opposition to this position. Initially, PSNH argued that the Seabrook Power Contract was a FERC filed contract that required the pass through of NAECo's actual cost of capital that could not be displaced by this Commission under the filed rate doctrine. PSNH also argued that the Commission had fully reviewed and approved the financings and capital structures at issue herein under RSA 369 and 362-C in DR 89-244 in approving the Rate Agreement. PSNH also contended that because of time constraints these bonds had to be issued in the name of PSNH prior to the creation of NAECo to meet the timing requirements of the Internal Revenue Code, and that under the terms of the notes they could not be transferred to NAECo. Finally, PSNH noted that the lower cost of debt of these notes will be reflected in PSNH's cost of capital in the current base rate proceeding. B. Office of the Governor The Office of the Governor objected to the fact that PSNH had failed to respond to four of CRR's data requests relating to the PCRBs by the conclusion of the hearings in this matter. The Office of the Governor repeated a concern raised by Staff that PSNH was failing to supply complete and accurate information to the Commission and the parties in what appeared to be a course of conduct designed to withhold financially detrimental information. Based on available data, the Office of the Governor concurred in CRR's position and recommended the Commission impute the lower cost of capital to the Seabrook Power Contract and pass those savings on to ratepayers. C. Campaign for Ratepayers Rights CRR argued that the proceeds from the low interest, tax exempt PCRB bonds issued by the New Hampshire Industrial Development Authority and its successor agency, the Business Finance Authority (hereinafter referred to jointly as the BFA), were inappropriately and illegally retained within the capital structure of PSNH when the assets for which they were issued were spun off to create NAECo. CRR maintained that the PCRBs were issued to finance qualifying pollution control facilities at Seabrook Station and that absent those facilities, these tax exempt bonds could not have been issued. Thus, the PCRBs equitably and legally belonged in the capital structure of NAECo and not PSNH. CRR contended that had these bonds been placed in NAECo's capital structure, ratepayers, rather than shareholders, would have received the benefit of lower interest rates during the Fixed Rate Period and that the Commission should impute those savings back to ratepayers. D. Office Of The Consumer Advocate The OCA shared CRR's belief that it was inappropriate for PSNH to hold tax exempt PCRBs when it no longer owns the pollution control facilities which were the basis for the issuance of the bonds. The OCA suggested the Commission order PSNH to request a letter ruling from the Internal Revenue Service (IRS) concerning the tax exempt status of the bonds. The OCA recommended that the Commission impute to the Seabrook Power Contract $212.5 million in lower capital costs garnered by PSNH during the Fixed Rate Period and require PSNH to refund those monies to ratepayers. E. Staff Staff concurred with PSNH's conclusion that the Commission had approved the proposed capital structure of PSNH and NAECo following the divestiture of Seabrook in DR 89-244 which included leaving $100 million in PCRBs in the capital structure of PSNH. Staff further noted that both the Governor and Council were explicitly informed by PSNH that all of the tax benefits of the additional PCRBs would flow to PSNH during the Fixed Rate Period and ratepayers thereafter. 7. Replacement Power Costs Incurred as a Result of Outages at Maine Yankee, Vermont Yankee and Connecticut Yankee A. Public Service Company of New Hampshire PSNH objected to the disallowance of replacement power costs at Connecticut Yankee as recommended by Staff. PSNH maintained Staff had not provided sufficient evidence to support its recommendation that all replacement power costs be disallowed for the outage that commenced when Connecticut Yankee shut down to address the design flaw with the Containment Air Recirculation (CAR) fans and concluded with Connecticut Yankee's decision to permanently shut down and decommission the plant. PSNH argued that its witness, Thomas Dente, had established that Connecticut Yankee acted appropriately in addressing the CAR outage and in moving up the refueling of the Unit while the CAR problem was addressed. PSNH further argued that Staff had failed to establish NAESCo acted imprudently, or negligently, with regard to the cause or duration of the outage. PSNH also objected to the recommended $11,000 replacement power disallowance for alleged imprudence at Vermont Yankee. PSNH argued that although Vermont Yankee personnel admittedly acted imprudently in failing to follow standard procedures, thereby causing the outage, a disallowance was inappropriate because there was no management imprudence. With regard to the Maine Yankee outage which commenced with the discovery of cable separation problems and, again, concluded with a decision to permanently shut down and decommission the unit, PSNH argued that it was necessary to refuel the plant and the decision to decommission the plant was made during that time period. Thus, any period for disallowance of replacement power costs should conclude with the beginning of the refueling outage which lasted until the decision to shut down was made. B. Office of the Governor The Office of the Governor supported Staff's recommendation that the Commission disallow the recovery of $2.9 million in replacement power costs because the power costs were incurred as a result of the imprudent operation of the Maine Yankee, Vermont Yankee and Connecticut Yankee nuclear generating stations. C. Office of the Consumer Advocate The OCA supported Staff's recommended disallowances. D. Staff Staff took the position that all replacement power costs for the outage that commenced when Connecticut Yankee came down to address the design flaw with the CAR fans and concluded with Connecticut Yankee's decision to permanently shut down and decommission the plant should be disallowed. Staff based its position on the belief that the problem with the CAR fans should have been addressed earlier than it was, and that this delay, along with a number of other problems that were discovered while the plant was down, led to the conclusion to decommission the unit. Staff took the position that the replacement power costs incurred for the outage at Vermont Yankee should be disallowed because the outage was due to the admitted negligence of Vermont Yankee personnel. Staff maintained that the fact that the personnel were adequately trained and that management was not involved in the negligent conduct were irrelevant to a determination of whether shareholders or ratepayers should bear the risk of employee negligence. Staff maintained that shareholders should bear the risk of negligent conduct by their agents. Staff also argued that all replacement power costs incurred as a result of the Maine Yankee outage should be disallowed. Staff maintained, and PSNH concurred, that Maine Yankee was required to come down when it was discovered that the control room had cable separation problems. In particular, it was discovered that the cables for the redundant manual trip buttons in the control room shared the same cable train. Thus, an accident affecting this single cable train might eliminate both redundant systems. Once the unit came down to repair this particular problem, a number of other cable separation problems for redundant systems were identified. Given the time that would be required to identify and correct these problems, the decision was made to refuel the plant. Subsequently, the decision was made by the owners to shut down and decommission the unit because it was no longer economic to operate. Staff contended that subsequent to a fire at one of the nuclear units located at Brown's Ferry in 1975 in which redundant systems were threatened by the same event due to the proximity of the cables operating the redundant systems, nuclear plants throughout the country were required to identify and separate cables for redundant systems to avoid this particular problem. Staff also testified that in 1990 and again in 1992 Maine Yankee was required to clean up some of its control room wiring problems and that had those efforts been conducted prudently, this particular outage would not have occurred. 8. Merrimack and Schiller Stations' Coal Pile Reconciliation Subsequent to the hearings in this matter, the OCA, PSNH and the Staff submitted the final reconciliation of the amount of coal held in inventory at Merrimack and Schiller Stations. Consequently, this issue is no longer in contention. 9. Seabrook Station Science Center A. Public Service Company of New Hampshire PSNH maintained that the costs associated with the Science and Nature Center (Center) should be included in rates because the Center was used and useful in the production of power. PSNH maintained that although the Center does contain exhibits on nuclear power and Seabrook Station for students and members of the general public, the building is also used for training and meetings. NAESCo testified that the building contains an auditorium that seats 100 people which is the only facility large enough to conduct a meeting of all of the plant's department heads. PSNH also noted that the Commission had specifically ruled that the Center should not be disallowed from PSNH ratebase on two prior occasions. B. Campaign for Ratepayers Rights CRR claimed that the Center was not intended to be included in the costs passed on to PSNH ratepayers because it was not included in Schedule I of the Seabrook Power Contract. CRR also argued that the Center was a "mini theme park" that should not be included in rates because it was not functionally related to the generation of power for customers. C. Office of the Consumer Advocate The OCA argued that the Center was designed and maintained for public relations purposes, and was therefore operated to promote nuclear power's and the owner's image. Without criticizing either goal the OCA noted that these were inappropriate costs to collect from ratepayers. 10. Appropriate Methodology for Calculating Replacement Power Cost Incurred as a Result of Imprudence A. Public Service Company of New Hampshire PSNH maintained that the Commission's methodology for calculating replacement power costs incurred as a result of imprudent outages at generating units was inequitable, unjust and unreasonable. PSNH argued that in calculating replacement power costs the Commission should utilize a net economic harm test. In applying this test to an imprudent outage, the Commission would be required to subtract from replacement power costs to be disallowed any benefits PSNH ratepayers received from the outage, such as, joint dispatch savings under the Sharing Agreement or capacity revenues under the Capacity Transfer Agreement. B. Office of the Governor The Office of the Governor argued that PSNH should not be allowed to recover any replacement power costs incurred as a result of imprudence. C. Office of the Consumer Advocate The OCA argued that the Commission had already addressed and rejected PSNH's proposed "net economic harm" test. The OCA argued that each event, the imprudent operation of the plant in question and the ability to sell power to the majority owner of a unit, should be addressed discretely. D. Staff Staff made the same arguments set forth in the position of the OCA above. 11. Appropriate Calculation of "BA" Following the Fixed Rate Period All of the parties and Staff concurred that the "BA", or "Base Assumptions" component of FPPAC, must be consistent with the value set for this component in base rates. Thus, the computation of "BA" should have no effect on overall rates. 12. North Atlantic Energy Company, Inc.'s Purchase of the Vermont Electric Generation and Transmission Cooperative, Inc.'s Share of Seabrook and Harbor Seals A. Public Service Company of New Hampshire PSNH maintained that the purchase of Vermont Electric Generation and Transmission Cooperative, Inc.'s (VEG&T) 0.4129% share of Seabrook Station and its inclusion in the Seabrook Power Contract did not violate RSA 362-C as alleged by CRR. PSNH maintained it agreed to purchase VEG&T's share of Seabrook through its affiliate, NAECo, in settlement of a claim in the VEG&T bankruptcy. PSNH argued that the State and PSNH agreed to a modification to the Seabrook Power Contract and, therefore, the Rate Agreement that provided for NAECo's purchase of the 0.4129% VEG&T share of Seabrook and an agreement by PSNH to purchase the entire output of that share in accordance with the terms of the Seabrook Power Contract. The Agreement between the State and PSNH to modify the Rate Agreement was subject to the condition that NAECo's purchase of the VEG&T share of Seabrook and its subsequent sale to PSNH would not increase rates to PSNH ratepayers during the Fixed Rate Period. PSNH concluded that because there could be no change in rates during the Fixed Rate Period, and any increase in rates would occur after the Fixed Rate Period, there was no violation of the provisions of RSA 362-C:9. With regard to the fouling of the cooling tunnels with the carcasses of dead harbor seals caught in the intake of the cooling tunnels when the seals venture into the tunnel openings, PSNH testified that this has only recently become a problem with the resurgence of the harbor seal population in the Gulf of Maine. Thus, this was not a design flaw as the harbor seal was not perceived as a problem at the time of the design and construction of the cooling tunnels. B. Campaign For Ratepayers Rights CRR objected to ratepayers bearing the cost of the VEG&T share of Seabrook, which commenced at the conclusion of the Fixed Rate Period, June 1, 1997, because it violated the provisions of RSA 362-C:9. CRR also asked for a disallowance of any costs associated with remedying the harbor seal problem as it was a design flaw in the construction of the plant. Thus, ratepayers should not be required to bear the expense of this negligence. III. COMMISSION ANALYSIS Given the numerous issues raised in this proceeding, we will address each issue separately in the order that it was briefed by the parties and Staff. 1.(A) Capacity Transfer Agreement Revenues As a result of the nuclear outages in Connecticut, effective November 1, 1997, CL&P was unable to meet its capacity capability responsibilities under the rules of NEPOOL. Pursuant to one of the Capacity Transfer Agreements entered into between PSNH and CL&P, which is appended to the Sharing Agreement, CL&P was required to buy a proportional slice of PSNH's excess generating capacity whenever CL&P is unable to meet its NEPOOL capacity obligations. The designated percentage of PSNH unit capacity to be transferred under the Agreement is as follows: Seabrook 20.0% Millstone III 10.0% Merrimack I 7.0% Merrimack II 18.0% Schiller 4 5.0% Schiller 5 5.0% Schiller 6 5.0% Newington 20.0% Gas Turbines 10.0% Total 100.0% Exhibit 41 at 9. CL&P paid PSNH $27.4 million for the transfer of this capacity and its attendant energy. As is set forth above, the dispute in this case is the appropriate rate treatment of the $27.4 million paid to PSNH in compensation for the transfer of capacity to CL&P. PSNH argued that the revenues were appropriately booked to base rate revenues because the FPPAC formula did not include a provision for the flow back of capacity transfer revenues to ratepayers and, presumably, because the majority of the generation comprising the transfer is booked to base rates. The other parties to the proceeding argued that the FPPAC formula could be construed in a manner to provide a mechanism to flow these revenues through to ratepayers. They also argued that, although a majority of this generating capacity is booked to base rates, it would be inequitable to book the revenues to base rates because ratepayers would never see the benefits of the transfer and shareholders would receive a windfall due to the mechanics of the historic test year used in traditional ratemaking methodology. We concur with these parties and Staff. Thus, we have concluded that the only equitable, just and reasonable treatment of the capacity transfer revenues is to pass the revenues back to ratepayers this FPPAC period through the FPPAC formula or, in the alternative, pursuant to our general ratemaking authority. Initially, we believe the FPPAC formula can be construed to provide for the flow-through of the capacity transfer revenues to ratepayers. The FPPAC formula found at Rate Agreement at p. D-91 reads as follows: [[[Enf + PCf + EA] FPPAC rate = - BA] x SFT] + PA [[[kWh Req X DE ] "PCF" is defined as the "forecasted purchased capacity expense", Rate Agreement at D-91, and also as "[t]he capacity costs associated with other system power and unit contract capacity purchases . . . ." Rate Agreement at D-103. Although these definitions are written in affirmative language, there is no prohibition on a negative capacity expense, in other words "PCf" could be a negative number. Thus, in this instance the purchased capacity expense would be a negative $27.4 million and placed in the FPPAC formula to lower the overall rate for fuel and purchased power to PSNH ratepayers. We believe this is the only logical conclusion that can be reached where $10 million of production penalty costs caused by the capacity transfer, the fossil generation fuel costs, the entire cost of the Seabrook Power Contract and all of the costs of the CAAA are being passed on to ratepayers through the FPPAC formula. With regard to any arguments that some of the costs of the transferred capacity are recovered through base rates and, therefore, the revenues should be passed through base rates, we note that any capacity purchase costs would not be borne through base rates but are FPPAC costs under "Enf". Thus, we conclude there should be parity under the FPPAC formula for capacity purchases and sales. Assuming, arguendo, we were to accept PSNH's argument that these revenues, or some portion thereof, cannot be passed through the FPPAC formula to ratepayers and that these revenues should appropriately be taken into account as part of a base rate proceeding, the result would be a windfall to shareholders. The capacity revenues would be booked more than a year out of test year for the current base rate proceeding. Accordingly, the benefit of that revenue would not be captured for ratepayers. We believe this is inappropriate. As the OCA correctly asserted, ratepayers are funding the generation resources that are the source of these capacity revenues, whether through base rates or the FPPAC rate and, therefore, equity requires that the revenues garnered from these resources be flowed through to ratepayers. The New Hampshire Supreme Court has held on a number of occasions that the Commission's ratemaking authority under RSA 378:7 is plenary and that the Commission has general ratemaking authority under RSA chapter 378 to implement the method in which rates are put into effect. See, State v. New England Telephone and Telegraph Co., 103 N.H. 394, 397 (1961); Nelson v. Public Service Company of New Hampshire, 119 N.H. 327, 332 (1979). Thus, to the extent the FPPAC formula does not accommodate the flow-through of capacity revenues, we will exercise our general ratemaking authority and flow-through the $27.4 million in capacity transfer revenues to ratepayers concurrent with this FPPAC period. We take this action only to the extent necessary to avoid an injustice to ratepayers and a windfall to shareholders. 1.(B) Rate Agreement Breach In its testimony and its post hearing brief, Staff raised a number of concerns it characterized as a "potential breach" of the Rate Agreement. After reviewing the testimony of both Staff and PSNH, the Rate Agreement and the attendant Sharing Agreement, and Order No. 19,889 in DR 89-244 approving the Rate Agreement, Re Northeast Utilities/Public Service Company of New Hampshire, 114 PUR4th 385, 75 NH PUC 396 (1990), we have concluded that NU has engaged in a course of conduct which could be characterized as a breach of the Rate Agreement. Pursuant to Section 3 of the Rate Agreement, NU agreed to provide PSNH's capacity needs, should they arise, for a period of ten years following the First Effective Date under a Capacity Transfer Agreement. The Rate Agreement provides that this Capacity Transfer Agreement is designed to "assure an adequate supply of electric service to the ratepayers of New Hampshire . . . ." Rate Agreement at D-7-D-8. The executed agreement provides that NU will "at all times operate and maintain" the pledged generating units "in accordance with good electric utility practice." Capacity Transfer Agreement (CL&P to PSNH) at Paragraph 3. The Agreement also provides that NU will, "consistent with good electric utility practice . . . use reasonable efforts to assure that the [pledged Units] are operable at their applicable winter or summer Normal Claimed Capability Rating." Id. The nuclear generating stations, Millstone Units I, II, and III, comprise approximately 40% of the capacity pledged to PSNH by NU under this Capacity Transfer Agreement. Rate Agreement, Appendix F at D-112. The three Millstone Units have not operated for over eighteen months because of their failure to meet the requirements of the Nuclear Regulatory Commission (NRC). Both internal and external investigations of the cause of these outages indicate they are the result of management negligence at the highest levels of the NU organization. The three Units can no longer be claimed for capacity purposes and there is no clear indication that Unit I will ever return to service or that Units II and III will return to service soon. We believe there is a prima facie showing that NU's operation and maintenance of the Millstone Units has failed to live up to the language and intent of this Capacity Transfer Agreement. This leads us to question whether the State of New Hampshire may have been deprived of one of the fundamental benefits negotiated under the Rate Agreement. Tr. at 107-110. (November 14, 1997) Pursuant to Section 4 of the Rate Agreement, NU committed to enter into an agreement with PSNH "pursuant to which NU will credit [PSNH] with 50 percent of any . . . energy savings received under NEPOOL rules resulting from the combined operation of the NU system and [PSNH]." Rate Agreement at D-10. In a data response to a Staff interrogatory in this proceeding, NU/PSNH indicated that the changes to the NEPOOL agreement currently pending before the FERC would render the Sharing Agreement meaningless under the revised NEPOOL agreement pending approval before the FERC. Ex. 32, at 13-14. Our own review of NU/PSNH's response to that data request confirms Staff's testimony; the Sharing Agreement as it relates to energy savings and capacity is meaningless. Ex. 32, Att. MDC-6. Given NU's membership and status in NEPOOL, and the information and control that flow from that station, we find the failure of NU/PSNH to meet with the State to discuss the reformation of NEPOOL and its effect on the Sharing Agreement, under both the current regulatory regime and in a restructured environment, disturbing. The Sharing Agreement explicitly provides that [u]pon the determination that any term or other provision is invalid, illegal or incapable of being enforced, the parties shall negotiate in good faith to modify this Agreement so as to effect their original intent as closely as possible . . . . Sharing Agreement, at Section 11(c). While we understand the proposed changes to NEPOOL are necessary to implement the restructuring of the electric industry and that the restructuring of the industry would render these agreements, which address generation, meaningless, we are also cognizant that there will be some period of time during which bundled rates remain the status quo. Thus, to the extent the current regulatory regime remains in place, i.e., to the extent PSNH and the Initial System continue to own generation and generation continues to be bundled with transmission and distribution services, the NEPOOL Agreement and the Sharing Agreement and the economic assumptions underlying those agreements as originally crafted remain. Again, we believe NU/PSNH's failure to meet with the State to discuss the ramifications of the changes in the NEPOOL agreement and to discuss NU's positions and input into the proposed changes to the NEPOOL agreement may have deprived the ratepayers of New Hampshire the benefits negotiated under the Rate Agreement. The final issue relates to NU's filing of a "network transmission service" tariff at the FERC that replaced PSNH's and the Initial System's stand-alone transmission tariffs. The testimony revealed that PSNH ratepayers are annually losing millions of dollars in transmission revenues to the NU Initial System as a result of this new transmission tariff. The loss of revenues results from the fact that NU has treated the filing of the network transmission tariff as terminating those provisions of the Sharing Agreement and its attendant Capacity Transfer Agreements that provided for the payment to PSNH of transmission fees for the use of PSNH transmission facilities. It is telling to note that NU still charges PSNH, and thereby PSNH's ratepayers, transmission fees for similar transmission services that flow from PSNH to Connecticut and Massachusetts. NU failed to abide by the terms of the Sharing Agreement that required it to meet with the State and in good faith attempt to reform the agreements to retain the economic benefits to New Hampshire ratepayers for the use of the PSNH transmission system. Again, we believe this behavior has resulted in New Hampshire ratepayers losing the benefit of the bargains constructed within the Rate Agreement, the Sharing Agreement and the Capacity Transfer Agreements. With regard to all three of these issues, we believe the Attorney General's Office should investigate this course of conduct and take the appropriate action. We are concerned not only with the overall failure of NU to communicate with the State concerning the restructuring of NEPOOL as it relates to a restructured electric industry, but with the immediate economic consequences of that failure on PSNH ratepayers prior to the emergence of a competitive power market. 2. Treatment of "EA" Costs Following the Fixed Rate Period The "EA" component of FPPAC was designed to allow for an increase in rates above the projected seven annual 5.5% increases in rates during the Fixed Rate Period under certain extraordinary circumstances. One of the delineated circumstances was an increase in annual operation and maintenance expenses of at least $2 million or a capital expenditure of at least $20 million due to new environmental regulations. In DR 95-068 we determined, with qualifications, that PSNH's expenditures to comply with the CAAA had met the criteria for recovery of the costs of compliance under paragraph "EA". The conclusion of the Fixed Rate Period, which prevented PSNH from recovering these costs through a base rate proceeding, and PSNH's pending base rate proceeding led Staff to recommend that these costs now be collected through base rates in accordance with customary cost of service regulatory practice. We concur with Staff that operation and maintenance expenses and capital costs of generating facilities that were recovered through the FPPAC paragraph "EA" during the Fixed Rate Period and that are traditionally treated as base rate items should now be recovered through base rates following a base rate proceeding. With regard to incremental increases in costs associated with the CAAA that occur between base rate proceedings, we will address that issue when and if the issue becomes ripe. 3. Best Efforts Pursuant to Section 12 of the Rate Agreement, NU/PSNH agreed to use its best efforts to renegotiate the rates paid to thirteen of the State's largest and most expensive SPPs. There has been no determination, as yet, by the Commission as to whether PSNH has met its best efforts obligations under Section 12 with regard to eleven of the SPPs. See, DR 96-148. In reaction to PSNH's allegations in the temporary rate proceeding in DR 97-059 that any decrease in rates might force PSNH into bankruptcy, and because of concerns relative to the financial viability of PSNH's affiliates and its parent caused by the Millstone nuclear outages, Staff and the OCA argued that the Commission should defer recovery by PSNH of some portion of both past and projected SPP costs. Staff and the OCA argued that a deferral was necessary to ensure that ratepayers are adequately protected from an NU or PSNH bankruptcy should the Commission ultimately conclude that NU/PSNH failed to meet its best efforts obligations. We do not believe a deferral mechanism is necessary to protect ratepayers at this time. PSNH has already deferred recovery of approximately $200 million in SPP costs. Thus, if the Commission were to determine that NU/PSNH had not met its best efforts obligations under Section 12 of the Rate Agreement and that ratepayers had been harmed by that failure, any damages could be recouped through the disallowance of deferral recovery. 4. Light Loading The Commission opened DR 96-149 on its own motion on May 14, 1996 to investigate concerns that PSNH was purchasing power from SPPs during periods of "light loading" when such purchases should have been curtailed under state and federal law. In this docket, Staff and the Office of the Governor questioned PSNH's purchases from SPPs in light load situations and recommended the deferral of recovery of SPP costs when PSNH should have curtailed purchases. PSNH bears the burden of establishing the reasonableness of the rates it seeks to collect from customers. Based on the testimony of Messrs. McCluskey, Cannata and Staszowski, we believe there has been a prima facie showing that PSNH has failed to comply with federal law and the terms of the Commission's rate orders regarding periods when SPP purchases are not required. We reach this conclusion based in large part on PSNH's inability to provide this Commission with the information and documentation necessary to substantiate its assertions regarding negative avoided costs. Thus, we have concluded that we will defer PSNH's recovery of $10 million, half the amount PSNH indicated it was overpaying SPPs during periods of light load in DR 94-080. In the event PSNH can establish it has acted in accordance with the FERC rules implementing the Public Utilities Regulatory Policy Act (PURPA) and the rate orders applying the FERC rules, it will be allowed to recover these funds. 5. Unit II Parts In DR 94-172, PSNH, NAESCo, NAECo and the Commission Engineering Staff supported the creation of an imprudence mitigation fund. The proposed fund would be based on the value that Unit II parts to PSNH ratepayers. The OCA and the Commission Finance Staff argued that the proposal was inappropriate because PSNH ratepayers were already paying for Unit II parts through the Seabrook Power Contract. Finance Staff and the OCA based their position on the fact that the Rate Agreement allocated $700 million to all of PSNH's interest in Seabrook Units I and II. Thus, when the entire $700 million was allocated to Unit I under the Seabrook Power Contract, ratepayers were already compensating shareholders for any investment in Unit II parts. PSNH, NAESCo and NAECo responded that they had not recovered any of the "preserve and protect" costs for Unit II parts since the inception of FPPAC and that FPPAC did not explicitly provide for recovery of those costs. They also claimed that the regulatory treatment by the Commission up to that time, which allowed NAECo to recover the book value of Unit II parts placed into service in Unit I under the Seabrook Power Contract, established that Unit II parts were shareholder property. In rejecting the proposed imprudence mitigation fund, we implicitly concurred with the position of PSNH, NAESCo and NAECo by allowing the practice of charging ratepayers for Unit II parts to continue. We did not, however, explicitly rule on the contention by PSNH, NAESCO and NAECo that Unit II parts are the sole property of shareholders. In this proceeding, the OCA explicitly requested that we address the issue of the appropriate regulatory treatment of Unit II parts. Specifically, the OCA requested that we return to ratepayers NAECo's percentage of the profit from the sale of the Unit II steam generators. We believe the OCA has raised a valid issue that was not completely addressed in DR 94-172. Because this issue goes well beyond the Unit II steam generators and might require adjustments to NAECo's books for Unit II parts placed in service in Unit I over the past seven years, the appropriate compensation to NAESCO for inventory maintenance and further refunds to ratepayers because of other sales of Unit II parts, this issue should be addressed in a separate docket. Thus, we will open an investigation into the appropriate treatment of Unit II parts. 6. Pollution Control Revenue Bonds Prior to the divestiture of its Seabrook assets to NAECo, PSNH borrowed approximately $500 million through PCRBs issued by the BFA. At the time of their issuance, $287.5 million of the PCRB's were accorded tax exempt status. Subsequently another $119 million of PCRBs obtained tax exempt status during the Fixed Rate Period. The tax exempt status of the bonds significantly lowers their interest rates and, thereby, the cost of debt to the obligor. To qualify for PCRB tax exempt status, an entity must demonstrate to the IRS that the proceeds of the bonds will be used for very specific "qualifying facilities". When the BFA issued the $500 million of PCRBs, the proceeds of which were pledged to PSNH, the qualifying facilities were all associated with pollution control at Seabrook Station. At the time of the divestiture of Seabrook assets and liabilities to NAECo, however, PSNH did not divest these bonds with their attendant low interest rates to NAECo but, rather, maintained the bonds within the capital structure of PSNH. Because PSNH was under a form of price cap regulation during the Fixed Rate Period, rather than cost of service regulation, PSNH shareholders received the entire benefit of the lower interest rate PCRBs during the seven year Fixed Rate Period. If, however, PSNH had transferred the PCRBs to NAECo, along with the rest of the Seabrook assets and liabilities, at the time of the Seabrook divestiture all of the debt savings would have been passed on to PSNH ratepayers under the cost of service Seabrook Power Contract which flows through the FPPAC rate. Thus, during the Fixed Rate Period, PSNH ratepayers would have paid millions of dollars less than was actually incurred through the FPPAC rate. Following the Fixed Rate Period, PSNH ratepayers' share in the benefit of reduced debt costs through reduced costs are reflected in PSNH's capital structure used in cost of service regulation or the carrying costs ratepayers must bear for PSNH's uneconomic assets or stranded costs. CRR alleges, inter alia, that NU/PSNH never disclosed to the General Court and the Commission that it intended to finance the PSNH takeover with tax exempt PCRBs and that the interest rate benefits from the bonds would be retained by shareholders during the Fixed Rate Period. To remedy this situation, CRR has requested that the Commission impute the tax exempt interest rates of the PCRBs to NAECo for the purposes of the Seabrook Power Contract, which would result in a multi-million dollar refund to PSNH ratepayers. For the following reasons, we decline to take such action. In December, 1989, NU filed its petition initiating the Commission's review of NU's acquisition plan of PSNH pursuant to RSA 362-C and its approved bankruptcy reorganization plan. Along with the petition, NU filed testimony supporting the acquisition plan. The testimony of Robert Busch specifies that NU contemplated the possibility of retaining all outstanding PCRBs and seeking the issuance of millions of dollars of additional PCRBs to finance the acquisition. Furthermore, the Commission explicitly approved the issuance of additional PCRB financings, Re Northeast Utilities/Public Service Company of New Hampshire, 75 NH PUC 396, 474-477 (1990), and the record reveals that the Governor and Council also approved the issuance of additional PCRBs on August 22, 1990. The record further reveals that the Governor and Council were apprised by PSNH that the benefits of the bonds would not flow to ratepayers until the conclusion of the Fixed Rate Period. 7. Replacement Power Costs Incurred as a Result of Outages at Vermont Yankee, Maine Yankee, and Connecticut Yankee. In this proceeding, Staff argued that replacement power costs incurred as a result of outages at the Vermont Yankee, Maine Yankee and Connecticut Yankee nuclear power plants should be disallowed because the outages were the result of imprudence. The New Hampshire Supreme Court has held that when a utility has exhibited inefficiency, improvidence, economic waste, abuse of discretion, or action inimical to the public interest, costs incurred may not be passed on to ratepayers. Appeal of Seacoast Anti-Pollution League, 125 N.H. 708 (1985). The prudence standard is one of the specific standards that has been developed by the Court to govern the inclusion or exclusion of such costs for ratemaking purposes. Appeal of Conservation Law Foundation, 127 N.H. 606, 637 (1986). Prudence is "essentially ...an analogue of the common law negligence standard" requiring a utility to exercise due care in its activities. Id. The test of due care asks what a reasonable person would do under the circumstances existing at the time of a decision. Fitzpatrick v. Public Service Co. of New Hampshire, 101 N.H. 35 (1957). See generally, Re Public Service Company of New Hampshire, 81 NH PUC 531 (1996). We will apply this standard to the nuclear outages at issue herein. As a result of an employee's failure to follow proper procedures, Vermont Yankee experienced an unplanned outage. PSNH does not contest that a Vermont Yankee employee acted negligently, or imprudently, causing the plant to come down and that negligence caused PSNH to incur $14,000 in replacement power costs. PSNH argued, however, and Staff conceded, that the employee had been adequately trained. PSNH further argued that since "management" was not responsible for the outage, shareholders should not be penalized through a disallowance of the replacement power costs. It is a fundamental principle of law of agency that a master is responsible for the damages caused by the negligence of its agent. See, Restatement of the Law of Agency, Second 2, 216. We believe this is an appropriate and equitable result. Thus, we will hold PSNH responsible for the imprudence of its agent and disallow recovery of the $14,000 in replacement power costs. On December 5, 1996, Maine Yankee experienced an unscheduled outage because the manual reactor trip buttons were declared "inoperable" when it was discovered that the wires that operated each of the redundant systems were located too close to one another to meet technical specifications. Although it only took one day to correct the cabling for the manual reactor trip buttons, the discovery of this cable separation problem in the control room led to the investigation and discovery of a number of other cable separation problems throughout the plant. Further, because of the discovery of the problem with the manual reactor trip buttons, the NRC, through Generic Letter 96-01, ordered the plant to look at all circuits for operability. That investigation uncovered 10 to 20 other circuits that did not meet current standards for cable separation. This led the NRC to place Maine Yankee on Watch List, Category 2 because of general maintenance problems at the plant. On December 18, 1996, the NRC also issued a confirmatory action letter to Maine Yankee requiring the plant to remain off-line until all problems identified to date had been resolved. The confirmatory action letter specifically required the following actions by Maine Yankee: (1)complete the initial Generic Letter 96-01 review; (2)develop a plan and methodology for expanding the review to determine the extent of the cable separation problem, and to disposition the issues in accordance with the unit's design basis; (3)perform a root cause analysis that would address all hardware deficiencies identified and use the information to validate the "comprehensiveness" of the corrective actions; and (4) meet with the NRC to present the results and actions. Ex. 46 at 16 Because of the extensive planning and work required to resolve these issues, Maine Yankee determined it would take advantage of the required shut down to refuel the plant. At the same time, plant management began to review the economic viability of the plant. On August 6, 1997, the Maine Yankee Board of Directors voted to retire or decommission the Maine Yankee Nuclear power plant. Staff argued that all replacement power costs incurred from December 6, 1996, to August 6, 1997, should be disallowed because the costs incurred were the result of the imprudent operation and maintenance of the plant. PSNH argued that Maine Yankee prudently initiated a refueling of the plant while addressing the cable separation issues and other problems identified by the NRC. Therefore, the Commission should not disallow any replacement power costs incurred after the refueling of the plant commenced. Based on the testimony of Mr. Kokoszka that Maine Yankee had numerous opportunities to correct its cable separation problems beginning as early as the fire at Brown's Ferry in the mid-1970s to two required re-examinations of these problems in the early 1990s, we find the outage to be the result of the imprudent operation and maintenance of the plant and will disallow all replacement power costs resulting from the outage until the determination by management to retire the plant. Replacement power costs incurred between December 6, 1996 and August 6, 1997, therefore, are disallowed. In July, 1996, Connecticut Yankee experienced an unscheduled outage to effect repairs to the CAR fan systems. The CAR fans were declared inoperable when the plant's supply vendor, Westinghouse Electric Corporation (Westinghouse), issued a letter to all plants of the same design as Connecticut Yankee stating that the structural integrity of the service water cooling system could not be ensured under certain operating conditions. Westinghouse identified the potential problem in April of 1996 at Diablo Canyon nuclear power plant, a sister plant to Connecticut Yankee, and in June of 1996 officially notified all plants of this design of the potential problem. In July of 1996 independent contractors retained by Connecticut Yankee advised that the plant be brought down to effect repairs to the CAR fans. On July 22, 1996, the Plant was brought down to effect the repairs to the CAR fans. On August 9, 1996 management decided to move up the refueling outage that had been planned for September to coincide with the repairs to the CAR fan system. On August 17, 1996, the plant officially went into the refueling mode, which was scheduled to last 52 days. On October 9, 1996, the Connecticut Yankee Board of Directors announced that the preliminary results of an economic analysis of the continued operation of the plant indicated that the permanent shutdown of the Plant was likely. By October 9, 1996, the plant was no longer in the refueling mode, which would have been complete by that time but for the ongoing economic analysis of the plant. On December 4, 1996, the Connecticut Yankee Board of Directors made the final decision to permanently retire the plant. We find that the plant was prudently brought off-line to repair the CAR fans and that the decision to refuel the plant in August while repairs were effected to CAR fans was a prudent decision. Ratepayers should not, however, bear any costs for replacement power beyond October 9, 1996, when the plant would have completed refueling but for the preliminary decision to retire the plant. Ratepayers should not bear the costs incurred for replacement power while management considered whether or not it was in its best economic interest to retire the plant. Thus, we will disallow all replacement power costs incurred between October 9, 1996 and December 4, 1996. 8. Merrimack and Schiller Stations' Coal Pile Reconciliation By letter dated December 3, 1997, Staff provided the Commission with PSNH's final reconciliation for the coal inventories at Merrimack and Schiller Stations and the appropriate revenue adjustments associated with the reconciliations. The letter indicated that PSNH, the OCA and Staff had concluded that the final reconciliation of the coal inventories and the associated revenue adjustments were the appropriate revenue adjustments to be used in calculating the FPPAC rate. Given that the OCA raised this issue, and both Staff and the OCA, along with PSNH, concurred that the reconciliation filed with the Commission on December 3, 1997, appropriately reflected the coal pile inventories and the corresponding adjustments to revenue, we will accept the proposed adjustments as just and reasonable. 9. Seabrook Station Science Center As PSNH correctly noted, this issue has previously been addressed by the Commission wherein it was determined that the Science Center was in fact used and useful in the generation of electricity. See, Re Public Service Company of New Hampshire, 65 NH PUC 251, 259 (1980); Re Public Service Company of New Hampshire, 72 NH PUC 485, 492 (1987) ("Education Center" allowed in rates). We do not believe the record in this case is adequate to disallow the expenses of the Science and Nature Center. We believe there was sufficient testimony to establish that the Science and Nature Center is used for utility business purposes. 10. Appropriate Methodology for Calculating Replacement Power Cost Incurred as a Result of Imprudence PSNH has requested that we reconsider the decision in DR 96-077 in which we indicated that the use of a net economic detriment test to determine levels of replacement power disallowances for imprudent operation of a generating station was inappropriate. Re Public Service Company of New Hampshire, 81 NH PUC 531, 545 (1996). We decline to reconsider that decision and reiterate that we do not believe it is appropriate to offset the costs incurred because of the negligent operation of a generating unit with the revenues garnered as a result of that negligence from the sale of excess power. Our position is particularly appropriate where ratepayers have been required to cover all of the costs incurred by shareholders to own, operate and maintain the excess capacity used to generate that power. Furthermore, as indicated in DR 96-077, each act must be viewed discretely. To do otherwise would potentially obscure the result of management's imprudence. Id. 11. Appropriate Calculation of "BA" Following the Fixed Rate Period The "BA" component, or "Base Assumptions", of the FPPAC formula was intended to correct the FPPAC rate for those fuel and purchased power expenses incurred by PSNH that were being collected in base rates pursuant to PSNH's last traditional rate proceeding before filing for bankruptcy protection. Rate Agreement, at D-92. The Rate Agreement specified the exact amount of the BA component of FPPAC for each year of the seven years of the Fixed Rate Period. Rate Agreement, at D-106. The Rate Agreement did not, however, specify BA for the years following the Fixed Rate Period, although FPPAC is specified to run for three years beyond the Fixed Rate Period. Thus, it is unclear what value should be assigned to BA in years eight through ten of FPPAC. We believe the Rate Agreement contemplated a base rate filing following the Fixed Rate Period to address PSNH earnings following seven years of price cap regulation. Therefore, there was no need to specify a number to represent the hypothetical level of fuel and purchased power expenses in the "BA" component of FPPAC in the Rate Agreement because the actual numbers would be available to the Commission as a result of the base rate proceeding. Given that there is a base rate proceeding pending at this time, we will determine the level of fuel and purchased power expenses in base rates and reflect actual "BA" costs in FPPAC at the conclusion of the proceeding. 12. Costs Associated with North Atlantic Energy Company's Acquisition of Vermont Electric Generation and Transmission Cooperative, Inc.'s Share in Seabrook As is set forth above, PSNH's affiliate, NAECo, purchased VEG&T's 0.41259% share of Seabrook Station to resolve an issue in the VEG&T bankruptcy. In DR 93-092, the Commission approved the purchase and a modification to the Seabrook Power Contract proposed by PSNH and the Attorney General's Office that provided for the recovery of that share of Seabrook from PSNH ratepayers. Re Public Service Company of New Hampshire, 80 NHPUC 74 (1995). PSNH and the Attorney General agreed to increase the "BA" component of FPPAC to offset any rate increases that would result from this modification of the Seabrook Power Contract during the Fixed Rate Period. Re Public Service Company of New Hampshire, 79 NH PUC 5, 7-8 (1994). Because the Seabrook Power Contract Amendment did not increase rates during the Fixed Rate Period, it is not subject to the provisions of RSA 362-C:9. Thus, the Amendment was not subject to legislative approval. 13. Harbor Seals During the course of the past year, seven harbor seals have been entrapped and died in the intake tunnels of the circulation water system which provides cooling water to Seabrook Station. Testimony revealed that $118,000 had been expended this year attempting to remediate the problem and that management was attempting to find a design solution that would resolve the problem. CRR objected to the recovery of any funds expended at Seabrook Station to remediate the problem with harbor seals because the problem resulted from a design flaw by the owners. As was set forth in Section 7 above, the New Hampshire Supreme Court has held that when a utility has exhibited inefficiency, improvidence, economic waste, abuse of discretion, or action inimical to the public interest, costs incurred may not be passed on to ratepayers. Appeal of Seacoast Anti-Pollution League, 125 N.H. 708 (1985). The prudence standard is one of the specific standards that has been developed by the Court to govern the inclusion or exclusion of such costs for ratemaking purposes. Appeal of Conservation Law Foundation, 127 N.H. 606, 637 (1986). Prudence is "essentially ...an analogue of the common law negligence standard" requiring a utility to exercise due care in its activities. Id. The test of due care asks what a reasonable person would do under the circumstances existing at the time of a decision. Fitzpatrick v. Public Service Co. of New Hampshire, 101 N.H. 35 (1957). See generally, Re Public Service Company of New Hampshire, 81 NH PUC 531 (1996). The issue for our resolution, then, is whether there was a design flaw in the construction of the cooling tunnel intakes, such that a reasonable person of the requisite skill would have noted and corrected the flaw. The testimony revealed that the cooling tunnel intakes were designed to minimize their environmental impact. To achieve that goal, the intake structures were built very large to decrease the velocity of the water entering the tunnels so that fish would not become entrapped at the intake. At the time of construction, harbor seals were much less prevalent in the Gulf of Maine and were not perceived as a potential problem. In fact, it was 1993 before the first seal became entrapped in the tunnels. It appears harbor seals are only recently venturing inside the intakes and once inside become entrapped in the tunnels. Applying the prudence standard set forth above to the design of the tunnel intakes, we cannot conclude that a reasonable person of requisite skill and experience would have modified the design in a manner to prevent the current problem with harbor seals. Thus, we will not disallow the costs incurred as a result of seal entrapment or the cost of design modifications to address the situation. 14. Miscellaneous Staff also raised a concern relative to PSNH's failure to timely answer questions and to answer questions completely. Based on the record in this proceeding, we share Staff's concern. It appears PSNH has been unresponsive to data requests. We expect this practice to cease and direct PSNH to answer our Staff's and all parties' questions in a timely, thorough and comprehensive manner. Based upon the foregoing, it is hereby ORDERED, that Public Service Company of New Hampshire credit ratepayers for the $27.4 million in capacity transfer revenues received from Connecticut Light and Power Company this FPPAC period; and it is FURTHER ORDERED, that Public Service Company of New Hampshire meet with representatives of the State and the Commission to discuss those issues related to Joint Dispatch Savings, the Sharing Agreement and the Capacity Transfer Agreements under the current regulatory regime; and it is FURTHER ORDERED, that the operation and maintenance expenses and capital costs of generating facilities that are traditionally treated as base rate items and are currently being recovered through the "EA" component of FPPAC may continue to be recovered through FPPAC until they are included in base rates in the pending base rate proceeding; and it is FURTHER ORDERED, that there is no need for a best efforts deferral at this time; and it is FURTHER ORDERED, that Public Service Company of New Hampshire defer recovery of $10 million in Small Power Producer costs this FPPAC period; and it is FURTHER ORDERED, that the Commission shall institute an investigation into the appropriate treatment of revenues from Unit II part sales, the maintenance costs of Unit II parts, the appropriate treatment of Unit II parts placed into service in Unit I; and it is FURTHER ORDERED, that the retention of the Pollution Control Revenue Bonds in the capital structure of Public Service Company of New Hampshire was intended under the Rate Agreement; and it is FURTHER ORDERED, that Public Service Company of New Hampshire shall not recover the $14,000 in replacement power costs incurred because of the imprudent outage at the Vermont Yankee nuclear power plant; and it is FURTHER ORDERED, that Public Service Company of New Hampshire shall not recover the $2.9 million in replacement power costs incurred because of the imprudent outage at the Maine Yankee nuclear power plant; and it is FURTHER ORDERED, that Public Service Company of New Hampshire shall not recover the $461,000 in replacement power costs incurred at the Connecticut Yankee nuclear power plant after October 9, 1996; and it is FURTHER ORDERED, that the Science and Nature Center is used for utility business purposes and the expenses of the Science and Nature Center may be recovered through the Seabrook Power Contract; and it is FURTHER ORDERED, that it is inappropriate to offset the costs incurred because of the negligent operation of a generating unit with the revenues garnered as a result of that negligence from the sale of excess power; and it is FURTHER ORDERED, that the "BA" component of FPPAC shall be calculated in accordance with the last year of the Fixed Rate Period until it is established in the base rate proceeding; and it is FURTHER ORDERED, that we shall address the appropriate treatment of the modification of the Seabrook Power Contract to include the VEG&T share of Seabrook in the next FPPAC proceeding; and it is FURTHER ORDERED, that Seabrook Station's problem with harbor seals is not the result of imprudence. By order of the Public Utilities Commission of New Hampshire this tenth day of February, 1998. Douglas L. Patch Bruce B. Ellsworth Susan S. Geiger Chairman Commissioner Commissioner Attested by: Thomas B. Getz Executive Director and Secretary